Example 3.5



                    Consider the jobshop plant following the sequence shown in Figure 3.5(b) and described in Table E3.5.
                    Construct the Gantt charts for overlapping single-product campaigns for products A, B, and C and for the
                    multiproduct campaign with sequence ABCABCABC....


                    Table E3.5 Equipment Processing Times (in Hours) for Processes A, B, and C













                    Solution





                    The  Gantt  charts  for  the  three  processes  are  shown  in Figure  E3.5.  The  top  chart  shows  the  timing
                    sequences for each batch, and the next three charts show overlapping campaigns for products A, B, and C,
                    respectively. It can be seen that the rules and equations for overlapping campaigns given previously still
                    apply.  The  bottom  chart  shows  the  overlapping  multiproduct  campaign  using  the  sequence
                    ABCABCABC....  Note  that  there  are  many  time  gaps  separating  the  use  of  the  different  pieces  of
                    equipment, and no one piece of equipment is used all the time. This situation is common in jobshop plants,
                    and strategies to increase equipment usage become increasingly important and complicated as the number
                    of products increases.


                    Figure E3.5 Gantt Charts for Single-Product and Multiproduct Campaigns