Page 216 - Analysis, Synthesis and Design of Chemical Processes, Third Edition
P. 216

should give the same results as hand calculations using these charts.


                    When the data for equipment are entered, a list of the costs on the first worksheet is updated. The use of
                    the  spreadsheet  is  explained  in  the  CAPCOST.avi  help  files  contained  on  the  CD,  and  the  reader  is
                    encouraged to view the file prior to using the software. You are strongly advised to verify the results of
                    Example E7.14 for yourself prior to using the program to solve problems in the back of this chapter.


                    7.4 Summary





                    In this chapter, the different types of capital cost estimating techniques that are available were reviewed.
                    The accuracy of the different estimates was shown to increase significantly with the time involved in
                    completion  and  the  amount  of  data  required.  The  information  required  to  make  an  equipment  module
                    estimate based on data from the major process equipment was also covered. The effects of operating
                    pressure and materials of construction on the bare module cost of equipment were reviewed. Several
                    examples  were  given  to  show  how  the  installed  cost  of  equipment  is  significantly  greater  than  the
                    purchased  cost  and  how  the  installed  cost  increases  with  increased  pressure  and  materials  of
                    construction.  The  use  of  cost  indices  to  adjust  for  the  effects  of  inflation  on  equipment  costs  was

                    considered,  and  the  Chemical  Engineering  Plant  Cost  Index  (CEPCI)  was  adopted  for  all  inflation
                    adjustments.  The  concepts  of  grass  roots  and  total  module  costs  were  introduced  in  order  to  make
                    estimates of the total capital required to build a brand new plant or make an expansion to an existing
                    facility.  To  ease  the  calculation  of  the  various  costs,  a  computer  program  for  cost  estimation  was
                    introduced. This chapter contains the basic approach to estimating capital costs for new chemical plants
                    and expansions to existing plants, and mastery of this material is assumed in the remaining chapters.


                    References





                                  1. Pikulik, A., and H. E. Diaz, “Cost Estimating for Major Process Equipment,” Chem. Eng.
                                     84, no. 21 (1977): 106.


                                  2.  Peters,  M.  S.,  and  K.  D.  Timmerhaus, Plant  Design  and  Economics  for  Chemical
                                     Engineers, 4th ed. (New York: McGraw-Hill, 1991).


                                  3. Perry, R. H., D. W. Green, and J. O. Maloney, eds.,  Chemical Engineers Handbook, 7th
                                     ed. (New York: McGraw-Hill, 1997).


                                  4.  Cost  Estimate  Classification  System,  AACE  International  Recommended  Practice  No.
                                     17R-97, 1997.


                                  5. Ulrich, G. D., A Guide to Chemical Engineering Process Design and Economics (New
                                     York: John Wiley and Sons, 1984).


                                  6. Lang, H. J., “Engineering Approach to Preliminary Cost Estimates,” Chem. Eng. 54, no. 9
                                     (1947): 130.
   211   212   213   214   215   216   217   218   219   220   221