Page 230 - Beyond Decommissioning
P. 230

Experience and lessons learned                                    211

           restrictions on the pipe routing for the district heating. Further on, to fit those tunnels
           for preinsulated pipes would pose serious design and installation challenges, and the
           total cost of the network would be considerably higher than in other reuse options.
           However, if the steam plant is repurposed for new district heating, then the old steam
           pipe bridge and tunnel would be useful in directing the new pipes from the plant to the
           site boundary (following a careful structural analysis). In summary, the project con-
           sultants highlighted the following conclusions for their clients’ consideration:

           l  Depending on its soundness, it can be an advantage to the future district heating infrastruc-
              ture to reuse the section of the steam tunnel linking the steam plant building to the borders of
              the Ford site.
           l  The sand tunnels do not provide an adequate network for new energy infrastructure to and on
              the main redevelopment site. They might be envisaged for other forms of reuse (St.
              Paul, 2014).

           Another relevant case is the Battery Street Tunnel in downtown Seattle, WA, USA.
           Local authorities wanted to use it as a disposal site for the rubble of a demolished via-
           duct; however, local residents loved the old structure, and wanted it converted into a
           mushroom farm, recycling center or wastewater store. It was also proposed that the
           site could become a park, an exciting ride (e.g., a roller coaster) at an amusement park
           or a mix of several uses.
              For example, the tunnel could hold almost 50,000 m3 of water. Some sewer pipes
           pass right above the tunnel, and some below. The vision was to create a key piece of
           ecological infrastructure, and not just a container. A plant for capturing and filtering
           sewage could be installed in the tunnel. Or better, the water filtration could be com-
           bined with industrial uses of the filtered water.
              The promoters of the tunnel reuse launched a campaign to freeze any project for the
           tunnel until a productive use can be found. The debate was still open in November
           2017 when the article quoted by Crosscut (2017) was written. Unfortunately, a few
           months later, as reported by Seattle (2018) the City Council voted that the tunnel will
           be filled with viaduct demolition debris and sealed off. It was reported that the main
           driver for this outcome was the cost of doing seismic upgrades and other rehabilitation
           work on the tunnel, which could cost from $75 to $100 million, depending on the
           adaptive reuse selected. Apparently, the use of the tunnel as a waste dump does
           not require these expenses.
              The site described in Zillow (2013) and converted into a home is designed to with-
           stand explosions, earthquakes, and nearly all natural disasters thanks to its thick con-
           crete walls. The site in question is a relic from the Cold War, when the US were
           developing the Atlas missile system and installed the missiles in bases throughout
           the country. In the late 1960s, these sites were decommissioned and sold to be private
           dwellings or for other uses. In this home, the missile was placed in an underground silo
           linked to the missile launch control center. The silo is 55 m deep   15 m in diameter
           and could be adapted to the buyer’s desires. For example, it could be converted into an
           organic vegetable farm, hydroponics, precious metal vault, scuba diving school, or a
           test facility. Wichita Eagle (2006) reports a number of different reuses for under-
           ground facilities of this type. It also indicates a potential redevelopment issue, that
   225   226   227   228   229   230   231   232   233   234   235