Page 84 - Beyond Decommissioning
P. 84

The phases of redevelopment                                        65

              A nonnuclear project (the Seaholm Power Plant, Austin, Texas) casts further light
           on the need of early, orderly, and systematic planning for reuse. At Seaholm, a public
           opinion movement prevailed in a campaign to get the City Council to direct the City-
           owned Electric Utility to decommission the plant. The plan included dismantling the
           power-generating equipment and support systems, while tackling environmental
           worries. However, no reuse option had been selected in detail. Not knowing the future
           of the facility introduced conflicts in the decommissioning process. For example, the
           supporters of a Science and Technology Center wanted to keep large parts of the plant
           equipment onsite on display. This included retaining items ranging from gauges and
           chart recorders to a turbine generator set and the steam boilers. Other stakeholders
           wanted the equipment totally dismantled and taken away with only the bare shell
           of the building remaining. Likewise, there was a heated debate about whether to dis-
           mantle the boilers or address the asbestos and metals-based paint while maintaining
           the visual profile of the facility on esthetic grounds. All of these differing viewpoints
           occurred in parallel with the Electric Utility committing to be responsible for plant
           decommissioning and urging to get rid of any future liability at the facility, such as
           asbestos remaining in situ. These conflicts increased uncertainty during implementa-
           tion of decommissioning (Scadden, 2001). Eventually the redevelopment project was
           completed and Austin’s former electrical power plant, now a multiuse complex,
           houses residential spaces, offices, retail shops, restaurants, a library, and a hotel.
              It is important to prepare facilities/sites for rehabilitation or redevelopment. It
           is especially critical to stabilize buildings which might be rehabilitated, so that all
           deterioration is halted. The overall consensus is that those responsible for obsolete
           facilities should tackle ongoing and impending problems before these worsen. Con-
           tamination from decades of industrial activity has left many industrial buildings with
           hazardous materials in their soil or in the buildings. This contamination can pose
           safety and health risks, if left in situ, and can leave a community endangered if the
           industrial sites are deserted. Thus, contamination can present significant barriers
           to the adaptive reuse of industrial buildings both in extra costs and time. According
           to the Environmental Protection Agency (EPA), brownfields sites are “abandoned,
           idled, or under-used industrial and commercial facilities where expansion or rede-
           velopment is complicated by real or perceived environmental contamination”
           (Cantell, 2005).
              The location of contaminants and hazardous materials in industrial buildings can be
           predicted to some extent, although a characterization campaign will be required on a
           case-by-case basis. In addition to radioactive or chemical contamination in certain
           facilities, most older industrial buildings will contain asbestos, lead-based paint,
           and other heavy metals. Asbestos typically can be found in piping insulation, ducts,
           wires, floor tiles, plaster, etc., while lead is found in plumbing systems. New technol-
           ogies can mitigate such problems, including methods that take account of historic
           fabric. For example, contaminated architectural features and items can be encapsu-
           lated so that they can be preserved in situ. Alternatively, contaminated items can
           be removed or enclosed within new construction.
              After stabilizing the site, property owners should estimate the (technical, financial,
           human) resources to rehabilitate or redevelop their properties: although in principle
   79   80   81   82   83   84   85   86   87   88   89