Page 67 - Biomass Gasification, Pyrolysis And Torrefaction Practical Design and Theory
P. 67

46                           Biomass Gasification, Pyrolysis and Torrefaction



                 Total unit of electricity produced 5 7446 h 3 1kW 5 7446 kW/year
                 Variable O&M 5 $0.0031/kW h 3 7446 kW h 5 $23.08/kW/year
                 Yearly fixed O&M 5 $31/kW/year
                 Total O&M 5 23.08 1 31 5 $54.08/kW/year
                 Total revenue requirement 5 $54.08 1 $223.69 5 $277.68/kW installed/year
                 For 40 MW plant RR 5 40,000 3 277.68 5 $107,200/year



            SYMBOLS AND NOMENCLATURE
            F          fuel input to the gasification plant (tons/h)
                       specific capacity of a new gasifier plant ($/MWe)
            K g
            MW         capacity of a new gasifier (MW)
                       specific capacity of an existing gasifier plant ($/MWe)
            K g0
                       capacity of an existing gasifier (MW)
            MW 0
            c          constant, depending on the gasifier equipment and capacity ( )
                       total cost of a new gasifier ($)
            C g
                       total cost of an existing gasifier ($)
            C g0
            n          capacity index ( )
            C gA       capital cost in a certain year ($)
            C gB       capital cost in a past year ($)
            I A        cost index for year A ( )
            I B        cost index for year B ( )
            CC         capital cost of a plant ($)
            C fp       cost of fuel preparation ($)
            C tg       cost of turbine generator system ($)
            C e        cost of auxiliary plant ($)
            TPC        total cost of the plant ($)
            C con      cost of construction of the gasification plant ($)
                       cost of project development ($)
            C proj
                       office cost and contingency ($)
            C cont
                       process contingency cost ($)
            C cont, tech
                       project contingency cost ($)
            C cont, proj
            TPI        total project investment for a new plant ($)
            AFDC       interest paid on the borrowed capital ($)
            TCR        total capital requirement ($)
                       funds required for start-up expense ($)
            C start
                       working capital required ($)
            C wc
                       funds required for the initial catalyst and other supplies ($)
            C ca
            TOE        total operating expense in a biomass plant ($)
                       variable operating costs ($)
            O&M variable
                       fixed operating costs ($)
            O&M fixed
                       return on debt ($)
            R D
                       return on equity ($)
            R E
            D B        book depreciation ($)
            T          income tax ($)
            RR         the total revenue required from sales of all products from the plant ($)
            C c        carrying charge ($)
   62   63   64   65   66   67   68   69   70   71   72