66                                                                                Boiler Operator’s Handbook


               ery time, once you have it set.                      lected procedure should be submitted to, and approved
                    Now that you can get a main flame it’s a good time  by, the manufacturer.
               to review the process. Open valves admitting fuel to the     The contractor may say “we always did it that
               furnace only after purge and low fire position interlocks  way;” but that doesn’t make it right; insist on a written
               are proven. Open the valves in the main fuel only after  document. Be certain to remove brass, copper or bronze
               a pilot (ignitor) flame is proven. Prove the purge limits  parts exposed to the boiler water because the caustic
               prevent completion of a purge cycle when combustion  water can damage them. In many instances that includes
               air is blocked by blocking it. Ensure the purge require-  the safety valves. Replace them with overflow lines run
               ments are not satisfied when the burner register(s)  to a safe point of discharge where any liquid that passes
               is(are) closed, when the fan inlet is blocked to the degree  through can be collected and treated. Be prepared to
               the required air flow cannot achieve the specified flow  dispose of the boil-out chemicals after the process is
               rate and when the boiler outlet is similarly blocked. En-  completed.  Sometimes  it’s necessary  to  interrupt the
               sure the burner start-up cannot continue after purging  dry-out procedure to dump the boil-out chemicals,
               until the low fire position is proven. Admit main fuel  flush, and refill the boiler. Have a procedure in place for
               only after observing a stable and adequate pilot flame  re-establishing the dry-out. Be prepared to commence
               exists and extinguishes at the end of the main flame trial  normal water treatment immediately after the boil-out.
               for ignition period (unless there are separate pilot and     Don’t rush these steps, pushing activity along at
               main flame sensors where you assure the main flame  this point can damage the boiler in a manner that will
               sensor does not detect the pilot flame). Purge the boiler  last its lifetime. Have adequate personnel on hand for
               completely according to the code after each test or fail-  the maximum period required because it is not unusual
               ure to produce a main flame. Don’t alter flame trial tim-  to start and stop the boiler frequently during the initial
               ing of the control.                                  phase of a dry-out. It’s also possible for the procedure to
                                                                    take much more than an eight hour shift. On any large
               Boil-out and Complete Dry-out                        boiler it’s common for it to take more than a day.
                    This normally only applies to a new boiler. You     Normally the dry-out and boil-out are performed
               may have to boil-out a boiler after tube replacements or  with controls in manual for minimal adjustments as
               complete dry-out of some refractory repair so follow the  necessary to obtain a clean burning fire. You started the
               sequence when necessary. The entire process is skipped  dry-out  before  beginning  boil-out  and  will  probably
               for normal operation of a boiler.                    end up finishing boil-out before the dry-out is complete.
                    Some boilers will have pipe caps or plugs in casing  That’s because you don’t produce any steam pressure to
               drains where moisture can escape during dry-out. They  speak of while boiling out so the temperature is only a
               should be removed for this period of operation.      little over 212°F when the boil-out is complete.
                    Normally the boiler is simply filled with treated     You’ll have to let the boiler cool some before drain-
               makeup water or feedwater before this stage. Once  ing the boil-out chemicals and refilling it but there’s no
               the process begins that will have to change. Boil-out  harm in dropping them while the boiler is hot. There
               chemicals should be as prescribed by your boiler water  are two arguments about dropping boil-out water; one
               treatment supplier or the boiler manufacturer. Be certain  is solids will stick to the metal and bake on so allowing
               you don’t have conflicting requirements. Handle those  the water to cool is best, the other is they will retain the
               chemicals with extreme care and using all the required  solids while hot but drop them out if they’re allowed
               protective clothing and equipment; they’re a lot tougher  to cool so dumping the water hot is best. I happen to
               than normal chemicals. They should be added right be-  believe the second argument but always look for recom-
               fore you start the boil-out and dry-out and removed as  mendations of an appropriate temperature to drain the
               soon as the boil-out is done.                        water from the boiler and chemical manufacturers.
                    Burner operating time should be limited until       The boil-out water is considerably more caustic
               the boiler is operational and you’ve completed refrac-  than normal boiler blowdown so you should provide
               tory dry-out and boiler boil-out. When it’s possible to  for proper disposal of that water, neutralizing it before
               operate the boiler on main flame, make the first step a  dumping it in the sanitary sewer or employing a li-
               combined refractory dry-out boiler boil-out procedure.  censed hauler to dispose of it.
               Neither function can be performed without having an      Once the boil-out chemicals are drained the boiler
               effect of the outcome of the other. Procedures supplied  water  must  be  treated. The  boil-out  removed all the
               by the boiler manufacturer should be followed or the se-  varnish and grease that was covering the inside of the