ABOVE-GRADE WATERPROOFING  3.55

























                              FIGURE 3.41 Aggregate being applied into top coat, followed by back rolling.
                              (Courtesy of Coastal Construction Products)


























                              FIGURE 3.42 Mechanical broadcasting of aggregate into deck coating. (Courtesy of
                              Coastal Construction Products)
                         coating. Some primers must be allowed to dry completely (concrete); others must be
                         coated over immediately (metal). In addition to primers, some decks may require an
                         epoxy vapor barrier to prevent blistering from negative vapor drive.
                            Because of the volatile nature and composition of deck-coating materials, they should
                         not be installed in interior enclosed spaces without adequate ventilation. Deck coatings are
                         highly flammable, and extreme care should be used during installation and until fully