Page 26 - Coulson Richardson's Chemical Engineering Vol.6 Chemical Engineering Design 4th Edition
P. 26

9
                                             INTRODUCTION TO DESIGN
                   specification and chemical engineering design of equipment. In a typical organisation,
                   this phase is the responsibility of the Process Design Group, and the work will be mainly
                   done by chemical engineers. The process design group may also be responsible for the
                   preparation of the piping and instrumentation diagrams.
                     Phase 2. The detailed mechanical design of equipment; the structural, civil and electrical
                   design; and the specification and design of the ancillary services. These activities will be
                   the responsibility of specialist design groups, having expertise in the whole range of
                   engineering disciplines.
                     Other specialist groups will be responsible for cost estimation, and the purchase and
                   procurement of equipment and materials.
                     The sequence of steps in the design, construction and start-up of a typical chemical
                   process plant is shown diagrammatically in Figure 1.4 and the organisation of a typical
                   project group in Figure 1.5. Each step in the design process will not be as neatly separated
                   from the others as is indicated in Figure 1.4; nor will the sequence of events be as clearly
                   defined. There will be a constant interchange of information between the various design
                   sections as the design develops, but it is clear that some steps in a design must be largely
                   completed before others can be started.
                     A project manager, often a chemical engineer by training, is usually responsible for the
                   co-ordination of the project, as shown in Figure 1.5.


                                     Process section
                                                             Construction section
                                     Process evaluation      Construction
                                     Flow-sheeting           Start-up
                                     Equipment specifications

                                                              Procurement
                                                              section
                                                              Estimating
                                               Project
                                               manager        Inspection
                                                              Scheduling


                                         Specialist design sections
                                     Vessels                      Layout          Piping         Heat exchangers
                                                                                             valves        fired heaters
                                     Control                       Civil work
                                     and instruments         structures      Electrical
                                                                        buildings
                                     Compressors
                                     and turbines               Utilities
                                     pumps
                                             Figure 1.5.  Project organisation


                     As was stated in Section 1.2.1, the project design should start with a clear specification
                   defining the product, capacity, raw materials, process and site location. If the project is
                   based on an established process and product, a full specification can be drawn up at
                   the start of the project. For a new product, the specification will be developed from an
                   economic evaluation of possible processes, based on laboratory research, pilot plant tests
                   and product market research.
   21   22   23   24   25   26   27   28   29   30   31