Page 257 - Design of Simple and Robust Process Plants
P. 257

6.4 Application of Reliability Studies for a Process and Utility Plant  243

                  Case 3                  Case4
                         100 t/hr
                 Boil 1
                                          253 t/hr
                         100 t/hr         New
                 Boil 2                   boiler      253 t/hr
                                          253 t/hr
                         150 t/hr         New
                                          boiler
                 New                                  253 t/hr
                 boiler
                                          253 t/hr
                         150 t/hr         New
                                          boiler
                 New
                 boiler                               253 t/hr
                                          253 t/hr
                         150 t/hr         New
                                          boiler
                 New
                 boiler


                Fig. 6.10. Alternative designs of a co-generation plant.

                ferent cases a forced outage during a scheduled maintenance stop of one of the
                units does not necessarily result in a shortage of steam.
                  The objective of the study was to quantify reliability of the steam supply for the
                different design cases. The reliability of the power supply was outwith the scope of
                the study, and it was assumed that a sufficiently sized external power supply was
                available as back-up.
                  The results of the study should be used as input for an economic evaluation to
                optimize investment in utility plant reliability versus cost of a temporary reduced
                steam supply. The cost of a reduced steam supply might be minimized by the appli-
                cation of an on-line steam load-shedding system, which has the advantage of avoid-
                ing total site outage by selectively shutting off steam consumers. These systems
                operate in the same way as power load-shedding systems.


                Table 6.5. Full load steam capacity (Mton/h) for the different co-generation system cases.

                Cases     Max. MW   Max steam  One boiler in shut down  One turbine in shut down
                                    (Mton/h)  Max steam (Mton/h)  Max steam (Mton/h)

                Case 1    111       680      580                520
                Case 2A    80       500      400                425
                Case 2B    80       600      500                500
                Case 3    111       650      550                500
                Case 4    174       1010     760               1010
   252   253   254   255   256   257   258   259   260   261   262