Page 306 - Drilling Technology in Nontechnical Language
P. 306

Chapter 12 –  MANAGING DRILLING OPERATIONS                       297






                    Depth-dependent costs

                    Depth-dependent costs will increase as the well deepens. Typical
                 depth-dependent costs relate to casings, cement, completion tubings,

                 drilling fluid, and drill bits. These might form up to one-third of the total
                 well cost, unless problems occur that substantially increase the time-
                 dependent costs.


                    Support costs (overheads)



                    Overheads are the costs that are incurred by the office and other off-
                 rig activities. Examples include engineering work, such as data analysis
                 or studies, and support staff, such as secretaries, as well as a proportion
                 of the cost of the office. Some of these costs are time dependent and some

                 are fixed costs.


                    Contingency costs

                    There are some problems that can be expected to occur, with a small or
                 large probability that any particular problem will actually occur. The cost
                 of each event—the contingency cost—is the probability of its occurrence
                 multiplied by the cost if it actually does occur. Say that in a particular
                 hole section, offset data predicts that mud losses might occur. If the cost
                 of those losses might be $50,000 and the likelihood of losses is 10%, the
                 contingency cost is $5,000. An example estimate of contingency costs is

                 given in figure 12–4.

                    Accuracy of the estimate


                    There is one other element to the cost estimate. The accuracy of

                 the estimate (the confidence in the final figure) must be given. If good



                 offset data is available, the accuracy generally will be that the final cost
                 should be within 10% of the estimate, or, exceptionally, 5%. For an
                 exploration well, the accuracy will be considerably less—25% would be a
                 reasonable assumption.









        _Devereux_Book.indb   297                                                 1/16/12   2:12 PM
   301   302   303   304   305   306   307   308   309   310   311