Page 18 - Estimator's Piping Man-Hour Manual 5E
P. 18
Section One
SHOP
FABRICATION
OF
PIPE
AND
FITTINOS
It is the Intent and express purpose of this sec
tion to cover as nearly as possible all operations
which may be encountered in a shop engaged in
the pref abrication of process piping for any type
of industrial or chemical plant.
The man hours listed for the various operations
are for labor only, and have no bearing on ma
terials which must be added in all cases for a
complete labor and material estimate.
All labor for unloading from railroad cars on
trucks, storing in fabrication yard or warehouse,
hauling to fabrication area, fabricating and re
turning to storage area or loading for delivery
to erection site have been given due considera
tion in the man hours listed. No consideration
has been given to overhead or profit in any way.
For alloy and non-ferrous fabrication, apply the
percentages which appear under Section Three
to the following pages listing the various shop