Page 18 - Estimator's Piping Man-Hour Manual 5E
P. 18

Section One


                              SHOP

                             FABRICATION

                              OF

                             PIPE

                             AND


                              FITTINOS




                              It is the Intent and express purpose of this sec­
                              tion to cover as nearly as possible all operations
                              which may be encountered in a shop engaged in
                              the pref abrication of process piping for any type
                              of industrial or chemical plant.
                              The man hours listed for the various operations
                              are for labor only, and have no bearing on ma­
                              terials which must be added in all cases for a
                              complete labor and material estimate.
                              All labor for unloading from railroad cars on
                              trucks, storing in fabrication yard or warehouse,
                              hauling to fabrication area, fabricating and re­
                              turning to storage area or loading for delivery
                              to erection site have been given due considera­
                              tion in the man hours listed. No consideration
                              has been given to overhead or profit in any way.

                              For alloy and non-ferrous fabrication, apply the
                             percentages which appear under Section Three
                              to the following pages listing the various shop
                              fabrication operations.