Page 96 - Estimator's Piping Man-Hour Manual 5E
P. 96

Section Two-FIELD FABRICATION 79

            HANDLING AND ERECTING FABRICATED
                              SPOOL PIECES
                                  Carbon Steel Material
                       DIRECT MAN HOURS — PER FOOT BY SIZE

          Pipe                             SCHEDULE NUMBERS
          Size
         Inches            10 to 60             80 to 100        120 to 160
         1/4                0,26                  0.29             0.30
         3/8                0.27                  0.29             0.32
         1/2                0.27                  0.30             0.34
         3/4                0.28                  0.32             0.35
         1                  0.29                  0.34             0. 39
         1-1/4              0.30                  0.35             0.41
         1-1/2              0.32                  0.37             0.45

         2                  0.34                  0.40             0.49
         2-1/2              0.36                  0.44             0.54
         3                  0.39                  0.48             0.59
         3-1/2              0.40                  0.50             0.62
         4                  0.41                  0.52             0.66
         5                  0.44                  0.57             0.72
         6                  0.47                  0.64             0.84
         8                  0.57                  0.81             0.99

         10                 0.72                  1.00             1. 38
         12                 0.88                  1.23             1.69
         14 OD               1.01                 1.46             2.01
         16 OD               1.27                 1.71             2.34
         18 OD               1.48                 1.96             2.69
         20 OD               1.74                 2.22             3.04
         24 OD               1.94                 2.51             3.43

     Man hours are for labor only and includes handling and hauling from storage yard, unloading and
     rigging in place, and aligning. It does not include welding, bolt-ups, make-ons or scaffolding.
     See other pages for these charges.
     For brass, copper and everdur pipe, double above man hours.
     Units apply to any length spool piece or segment of work.