76   Section Two-FIELD FABRICATION

       HANDLING AND ERECTING STRAIGHT RUN PIPE

                            DIRECT MAN HOURS — PER FOOT
           Pipe                             SCHEDULE NUMBERS
           Size
           Inches            10 to 60             80 to 100       120 to 160
           1/4                0.16                 0.17             0.18
           3/8                0.16                 0.17             0.19
           1/2                0.16                 0.18             0.20
           3/4                0.17                 0.19             0.21
           1                  0.17                 0.20             0.23
           1-1/4              0.18                 0.21             0.24
           1-1/2              0.19                 0.22             0.27
           2                  0.20                 0.24             0.29
           2-1/2              0.21                 0.26             0.32

           3                  0.23                 0.28             0.35
           3-1/2              0.24                 0.30             0.38
           4                  0.25                 0.31             0.39
           5                  0.26                 0.34             0.43
           8                  0.28                 0.38             0.50
           8                  0.34                 0.48             0.65
           10                 0.43                  0.60            0,82
           12                 0.52                  0.73             1.00

           1400               0.64                  0.87             1.19
           18 OD              0.75                  1.02             1.39
           18 OD              0.88                  1.17             1.60
           20 OD              1.03                  1.32             1.81
           24 OD              1.15                  1.49             2.04

      Man hours include all labor for unloading and storing in yard, loading and hauling to erection
      site, and rigging and aligning in place. It does not include welding, bolt-ups, make-ons or scaf­
      folding. See respective pages for these items.
       For brass, copper, and everdur pipe, double above man hours.
   88   89   90   91   92   93   94   95   96   97   98