Section One-SHOP FABRICATION     73





     Descaling R. T. J. Flange Faces: Oxidation (scale) created in R. T. J. grooves of flanges because
        of Stress Relieving or Heat Treating should be removed and charged for at the foEowing
        man hours.

         Flange                                  Flange
          Size              Man                  Size                Man
         Inches             Hours                Inches             Hours
        3 or less            0.6                  14                 2.5

        4                    0.9                  16                 3.2
        6                    1.0                  18                 3.5
        8                    1.3                  20                 3.9
        10                   1.8                  24                 4.6
        12                   1.9
                                                  —                  —
     Miscellaneous X-Rays: If specified, the following X-Rays should be taken and charged accord­
        ingly. Slip-on Welds X-rayed will be charged the same man hours as a Butt Weld X-ray.
        Mitre and Nozzle Welds X-rayed should be charged at 50% more than the Butt Weld X-ray
        man hours.
        Lineal Welding X-rayed should be charged at 0.7 man hours per foot through 1" thickness
        and at 1.0 man hours per foot for thickness greater than 1". For alloys add 25% to these
        man hours.
     Preheating Coupling Welds: On any size you should charge the man hours of Preheating a 2"
        extra heavy Nozzle Weld.