36   Section  One-SHOP FABRICATION

         LARGE      O.D. PIPE END CLOSURES—PRESSURE
                                     TYPE


                                  Carbon Steel Material
                                 NET  MAN HOURS  EACH
     O.D.
                                     WALL THICKNESS  IN.
     Pipe
      In.     .375     .500    .750     1.00    1.25     1.50     1.75    2.00
      26      28.2     34.5    45.1     55.1     64.4    73.4     81.5    89.5
      28      29.8     36.4    48.3     59.1     69.1    78.5     87.1    96.1
      30      31.3     38.3    50.9     62.3     72.8    82.7     91.7    10 I.I
      32      32.6     39.9    53.0     64.8     75.8    86.1     95.5    105.3
      34      33.9     41.5    55.1     67.4     78.8    89.a     99.3    109.5
      36      35.1     42.9    57.0     69.7     81.5    92.6    102.7    113.3
      38      36.3     44.4    59.0     72.2     84.4    95.9    106.4    117.4
      40      37.8     46.2    61.4     75.1     87.8    99.7    110.6    122.0
      42      39.3     48.1    63.9     78.1     91.3    103.7   1 1,5.0  126.8
      44      40.6     49.7    66.0     80.7     94.3    107.1   118.8    131.0
      46      42.0     51.4    68.3     83.5     97.6    110.9   123.0    135.7
      48      43.4     53.1     70.5    86.2    100.8    114.5   127.0    140.1
      54      46.4     56.7     75.3    92.1    107.7    122.3   135.6    149.6
      60      49.6     60.7    80.6     98.6    115,3    131.0   145.3    160.3
              2.25    2.50     2.75     3.00    3.25     3.50     3.75    4.00
      26      97.2    105.8    113.1   120.3    128.7    134.9   141.4    148.2
      28      104.4   113.6    121.4   12!). 2  138.2    144.8   151.8    159.1
      30      109.8   119.5    127.7   135.9    145.4    152.4   159.7    167.4
      32      114.4   124.5    133.1   141.6    151.5    158.8   166.4    174.4
      34      118.9   129.4    138.3   147.2    157.5    165.1   173.0    181.3
      36      123.0   133.8    143.0   152.2    162.9    170.1   178.3    186.9
              4.25    4.50     4.75     5.00    5.25     5.50     5.75    6.00
      26      154.3   160.6    167.2   172.9    178.8    184.9   191.2    196.6
      28      165.6   172.4    179.5   185.6    191.9    198.4   205.1    210.8
      30      174.3   181.4    188.8   195.2    201.8    208.7   215.8    221.8
      32      181.6   189.0    196.7   203.4    210.3    217.5   224.9    231.2
      34   j  188.7   196.4    204.5   211.5    218.7    226.1   233.8    240.3
      36      194.6   202.6    210.9   218.1    225.5    233.2   241.1    247.9

     Construction:  End  closures  as such are  shop fabricated  closures; orange peel,  saddle, or flat  plate type.
     Preheating:  If specified  or  required  by  codes,  add  for this operation. See  man  hours for  preheating.