46   Section One-SHOP  FABRICATION

                MACHINE BEVELING PIPE FOR WELDING

                    "U" Type, "V" Type And Double-Angle Bevels


                                Labor For Straight Pipe Only
                                  Carbon Steel Material

                                 NET MAN HOURS EACH
               Standard   Extra Hvy.
        Pipe    Pipe&      Pipe&                SCHEDULE NUMBERS
        Size   O.D. Sizes  O.D. Sizes
       Inches  3/8" Thick  1/2 "Thick  20  30  40  60  80   100  120  140  160
      2" Or Less  0.33      0.36    ..   ..  0.33  ..  0.36  „   ..   ..  0.87
      2-1/2"     0.34       0.37    --   --  0.34  --  0.37  -        --  0.91

      3          0.36       0.39    --   --  0.36  --  0.39  -   --   ..  0.93
      4          0.39       0.42    ..   -   0.39  --  0.42  --  0.72     0.99
      5          0.40       0.50    --   --  0.40     0.50      0.78      1.06
      6          0.46       0.59    --   ..  0.46  --  0.59  --  0.83  ..  1 16
      8          0.63       0.91   0.63  0.63  0.63  0.81  0.91  1.05  1.18  1.32  1.87
                                                                    L
                                                                      —
      10         0.91       1.26   0.91  0.91  0.91  1.26  1.36  1.50  1.69  12.34  2.83
                                                               .|   •
      12         0.97       1.50   0.97  0.97  1.18  1.77  1.87  2.03 1  2.83  3.14  3.35
      14O.D.     1 .34      1.77   1.34  1.34  1.57  1.97  2.28  2.93  3.21  3.78  3.97
      16 O.D.    1.50       2.20   1.50  1.50  2.20  2.44  2.60  3.50  3.78  4.25  4.82
      18O.D.     1.89      2.68    1.89  2.20  2.68  2.99  3.21  4.25  4.54  5.10  5.95
      20 O.D,    2.28       2.99   2.28  3.07  3.31  3.54  4.54  5.01  5.29  6.14  6.99

      240.D.     3.46       4.41   3.46  4.65  4.88  6.14  6.33  6.90  7.65  8.60  9.73

      For bevels on the ends of bends or shop trimmed fittings, or mitre bevels, add 50% to the above man hours.
      For "lip" bevels, add 50% to the above man hours.
      For rolled down "lip" bevels, add 75% to the above man hours.
      Above man hours are for machine beveling only and do not include cutting or internal machining. See respective
      man hour tables for these  charges.
     All pipe sizes shown below the ruled line have a wall thickness greater than 7/8" and must have U-type or double
     angle bevels in accordance  with ANSI and ASME codes for pressure piping. Sizes above the ruled line are 7/8" wall
     thickness  or less. The man  hours shown above the  ruled line are  for bevels as required  for inert arc root  pass
     welding.
   58   59   60   61   62   63   64   65   66   67   68