Page 69 - Failure Analysis Case Studies II
P. 69

54

            for potential dynamic resonances, but with very large structures and large masses these intuitions
            can be misleading. The torsional stiffness of wire rope mooring lines, as compared with equivalent
            solid bars, is so low that the period of natural torsion oscillation can be quite high, and there is
            reason to believe from observed mooring line failures, that such motions can sometimes be excited
            by the environmentally induced motions of floating structures. If the torsional amplitudes are large
            enough, and vessel motions such as to allow very low tensions to occur, then the kind of torsional
            instability described above can develop. Indeed, the destranding in the mooring rope illustrated in
            Fig. 4 is thought to have been induced by just such behaviour.
              This kind of dynamic torsional problem is initiated by the torque developed in the rope which
            then causes rotation because of the different characteristics of the adjoining component. The use
            of a torque balanced  rope will effectively remove the rotational response and so overcome the
            problem, but operating procedures that always maintain a minimum tension would also avoid the
            rope being damaged.
              It is also worth noting that the components in series which excite this kind of counter rotation
            need not be rope and chain. Any torsionally mismatched pair will be susceptible, be they six strand
            and torque balanced ropes, unbalanced ropes of different construction, or even two ropes of the
            same construction but different diameter.






            8.  Problems encountered during installation

              Mooring installation operations provide numerous opportunities for torsion related problems.
            Apart from the tendency for a stranded rope to rotate under tension, one common mechanism for
            inducing twist is dragging the rope along the seabed [8]. This can happen when installing a wire
            rope mooring line deployed from a mobile unit. The problem  only becomes apparent when the
            tension  in the rope is relaxed, and distortion is induced  between fairlead  and a deck mounted
            winch. Reeling back onto the winch then causes miscoiling which can subsequently lead to severe
            crushing damage.
              The mechanisms which are the principal interest in this paper are those associated with raising
            and lowering components, and specifically, operations involving six strand ‘work wires’. Numerous
            operations which involve wire rope coupled to a chain that is lying on the seabed can induce twist
            in  the  chain,  which  can,  at  a  later  time,  be  transferred  into  yet  another  component.  If  that
            component is sensitive to imposed twist then the consequences can be very serious. An example of
            such a deployment, based on the problems  encountered during deployment of the P34 mooring
            system [ 11,  will be considered in detail and a hypothetical mechanism for the torsional damage to
            the P34 spiral strand mooring lines analysed.
              The operation to be analysed involves the installation of a mooring lined in 1000 m water depth.
            The original intent was that the completed line should consist of a conventional drag embedment
            anchor attached to somewhat in excess of 1000 m of chain, attached in turn to a spiral strand and
            thus to a floating production,  storage and offloading vessel (FPSO). The anchor and chain were
            to be pre-installed with the free end of the chain lying on the seabed attached to a six strand wire
            rope supported by a surface buoy. The particular  stage of the operation being considered is the
   64   65   66   67   68   69   70   71   72   73   74