Page 173 - Forensic Structural Engineering Handbook
P. 173

FIGURE 5.2  Collapse of this suspended cement plaster ceiling in a rail station during
                 rush hour resulted in two deaths and many injuries to commuters. This PATH station in
                 Jersey City, NJ was closed for nearly two weeks to allow for the inspection of all ceil-
                 ings, the installation of protective scaffolding in areas of similar construction, and to
                 allow engineers to conduct field investigations.































                        FIGURE 5.3  Portions of this brick facade rained down on the
                        sidewalk and adjacent buildings, forcing officials to immediately
                        close Madison Avenue. A temporary bridge was erected across
                        Madison Avenue to shield the public before it could be reopened
                        to traffic. In this photograph, additional unstable areas of brick
                        have been removed and other stabilization has been added.

                                          5.6