Page 182 - Forensic Structural Engineering Handbook
P. 182

THE FIRST STEPS AFTER A FAILURE          5.15

                           5    14'   6
                                         A
              3" topping and  W18
              3" insulation on  2-span deck
              4-3/4" slab with          8'
              2" metal deck
                             W12   (–6")
                Collapsed
                 area
                                        8'
                                         B
                               W18
              4-3/4" slab with
              2" metal deck
                                4-span deck
                Framing plan





                     Buckled ribs


                Creased both sides
               of intermediate beam



                   Cut for removal





                    Bearing area



                                     Puddle welds and blowouts
             FIGURE 5.11  Judicious retention of key components by early investigators allowed the authors’ firm to
             observe first-hand the as-built conditions of this metal deck that collapsed while concrete was being placed,
             and to observe the failure mode.

             Field Notes
             Field notes are the backbone of a solid documentation program. They may include:

             • A log of crucial activities
             • Sketches
             • Measurements
             • Reference to photographs, highlighting what is depicted or indicating the location
   177   178   179   180   181   182   183   184   185   186   187