Page 39 - Forensic Structural Engineering Handbook
P. 39

1.20              DESIGN AND CONSTRUCTION PRACTICES

           Design Documents
           • Design drawings (signed and sealed) by the architect, structural engineer, mechanical
            engineer, and other consultants.
           • Sketches issued by the architect, structural engineer, mechanical engineer, and other con-
            sultants.
           • Specifications issued by the architect, structural engineer, mechanical engineer, and other
            consultants.


           Contracts
           • Contract with the owner—Executed official agreement between owner and construction
            manager, or owner and general contractor.
           • Subcontracts—Executed official agreements between owner and subcontractors, or with
            owner’s agent, the construction manager and subcontractors, or general contractor and
            subcontractors.
           • Purchase orders—Executed official authorizations to purchase certain materials and
            labor required for the project.
           • Letters to and from all parties involved in the project.
           • All documented communication (faxes, e-mails, memorandums, transmittals, etc.).


           Submittals
           • Shop drawings prepared by individual subcontractors, suppliers and/or manufacturers pro-
            viding labor and/or material to the project. They illustrate how their product is built and
            accomplishes the intended design function. Drawings are submitted to the general con-
            tractor or construction manager who then submits them to the architect and/or engineers
            for review and approval for project conformance.
           • Manufacturers’ cuts or data sheets pertaining to the material and equipment made by the
            manufacturer which will be incorporated into the project. These are also submitted to the
            general contractor or construction manager for project conformance prior to their submis-
            sion to the architect and/or engineers for review and approval.


           Contractor Claims and Credit Documents
             Daily Work Report forms used by the general contractor or construction manager to ver-
             ify the human-hours and materials used to perform a subcontractor’s work. These report
             forms are essential when a subcontractor states that work performed constitutes an addi-
             tion to the contracted scope of work.
             Backcharge Order forms of the general contractor or construction manager are used to
             verify the human-hours and materials used to perform work which was included in a
             subcontractor’s scope of work but had to be performed by others; or to verify work
             required to repair damage caused by a another subcontractor.
             Subcontractor and Vendor Claims are for extra costs incurred over and above the actual
             contract or purchase order amount due to work or material provided that was beyond the
             original scope of the contract or purchase order. These claims can be billed for on a
   34   35   36   37   38   39   40   41   42   43   44