Page 37 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 37

Be st Practice 1.7
                                                                        Project Best Practices    Be st Practice 1.8


               Best
               Best
               Best Practice 1.7Practice 1.7Practice 1.7
               Machinery specialists must understand the processes in  Detailed RCFAs (Root Cause Failure Analyses) show that the ma-
               which the machinery will operate.                   jority of root causes of failure lie in unanticipated process condition
                  Review the Process Flow Diagram (PFD) and Process and In-  changes. Failure to incorporate these upset and unusual conditions on
               strument Diagram (P&ID) for each process on the project.  the appropriate equipment data sheets can:
                  Discuss the PFD and P&ID for each process with experienced    Extend project schedule by requiring machinery re-design
               process engineers from the process licensors, project team and/or    Result in significant cost adders for machinery re-design
               plant process engineers and operators.                Reduce machinery safety and reliability
                  Define the potential upset and unusual process conditions with the    Extend plant start-up
               experienced process engineers and operators.
                  Be sure that all upset and unusual process conditions are defined  Benchmarks
               on the appropriate equipment data sheets.           Since the late 1990s, due to increased process unit size and potential
                  Require that an experienced process engineer and operator be  daily revenue losses, we have required detailed process reviews be-
               part of the machinery project team, and that they attend all plan-  tween machinery specialists, process engineers and operators prior to
               ning sessions, specification and data sheet reviews, as well as  the issue of specifications and data sheets. This action has been
               all vendor meetings during the pre-selection, design and test  implemented for all projects large and small.
               phases.                                               Results from this best practice have been:
                                                                     Elimination of changes after issue of the purchase order
               Lessons Learned                                       Reduced machinery design time and early machinery delivery
               It is the writer’s experience that approximately 80% of    No surprises during plant start-up
               machinery failure root causes are due to process varia-
               tions that are not anticipated in the design phase.













               Best
               Best Practice 1.8Practice 1.8
               Require that critical machinery pre-bid meetings be prop-  meetings (numerous meetings) have had the following issues occur
               erly defined and carried out.                        during the later stages of the project, and during field operation:
                  Pre-bid meetings require that all technical details are discussed,    Delayed bid selection – adding weeks or months to the schedule
               with appropriate design changes, before a price is quoted.    Cost adders for items that were not defined or exceptions to
                  These meetings are not the same as bid clarification meetings,  specifications that were not resolved during bid clarification
               which review the vendor’s bid after a price is quoted.    Delays in the manufacturing schedule for incorporation of items not
                  Pre-bid meetings, held separately with each quoting vendor, ensure  resolved during the bid phase
               that each vendor’s scope, design experience and exceptions to    Lower field reliability and possible safety issues resulting from
               specifications will be similar.                        selection of the low cost bidder
                  Vendors must be advised in the ITB of the requirements, time
               and agenda for these meetings in order to minimize project schedule.  Benchmarks
                                                                   The pre-bid meeting approach has been used since 1975 in all critical
                                                                   equipment selection since 1975. This has produced machinery of
               Lessons Learned
                                                                   optimum safety and reliability (compressor trains ¼ 99.5%þ). Pre-bid
               Failure to have pre-bid meetings can reduce critical ma-
                                                                   meetings have been used in all of the following industries globally:
               chinery safety and reliability, and significantly increase bid    Upstream oil and gas – offshore and onshore
               evaluation time.                                      Refining
                  Clients that have renounced pre-bid meetings, and have opted for    Chemical
               bid clarification discussions (endless emails and conference calls) or    Co-generation




              B.P. 1.8. Supporting Material                        a prototype, design and manufacturing audits have already
                                                                   been initiated and will be ongoing. If the equipment contains
              Once the ITB has been released to the quoting vendors, the  multiple major components that do not have field experience,
              work begins. The first order of business is to prepare for the  audits are required in this phase. These facts are shown in
              audits required at this stage. If the equipment in question is  Figure 1.8.1.

                                                                                                                11
   32   33   34   35   36   37   38   39   40   41   42