Project Best Practices    Be st Practice 1.8
              Suggested vendor pre-bid meeting details                are required to participate in the pre-bid meetings. Note:
                                                                      end user ‘in-house’ specialists are required.
              letter
                                                                   2. Individual supplier meetings – individual meetings are held
                                                                      with each supplier, using notes from previous meetings, to
              The following are suggested letter contents. Comments for  ensure equal supplier experience, scope and exceptions to
              consideration are noted in bold.                        specifications.
                Please be advised that you will be asked to attend a pre-bid
              meeting at ____________ (Your or Contractor’s or Company .  3. Meeting duration – Anticipated to be 1–2 days per major
              decision required) offices.                              equipment train, depending on machinery risk classification.
                                                                      Note: this includes compressors, drivers and auxiliaries.
                                                                      Please refer to the typical agenda below.
                Note: If possible, the meeting should be held at the vendor’s
                                                                   4. Typical pre-bid meeting activity – Technical details are
              offices. This is advisable since more experienced specialists are
                                                                      reviewed using agenda requirements, to ensure proven
              immediately available to answer any questions that may arise. This
                                                                      component experience (with impellers, diffusers, rotor
              decision should also be influenced by the machinery risk classifi-
                                                                      response, bearing, seal, and auxiliary system etc.), and to
              cation. The higher the risk, the more important the vendor office
              meeting is.                                             scope compliance and acceptable exceptions to specifications.
                The pre-bid meeting will take place approximately _______  Modifications are made, as necessary, to ensure that each
                                                                      vendor is offering proven components within acceptable
                                                                      design limits.
                (2–4 weeks after receipt of bid and must be coordinated
              with the project team . note this decision will also be influ-  Manufacturing capabilities are confirmed and sub-suppliers
              enced by the machinery risk class).                     for all major components and auxiliary systems are
                Only technical details will be discussed. Please bring the  identified, and their experience is confirmed for similar
                                                                      component manufacture.
              technical, un-priced proposal for the equipment that you will
              quote (trains include compressor, gear (if applicable) turbine  At the conclusion of the meeting, notes are reviewed and each
              and auxiliary systems). Your representatives at the meeting  vendor is instructed to submit a final priced proposal, in full ac-
              must include an experienced application instrument engineer  cordancewithmeetingnotesthatwillbeusedforthebidevaluation.
              and any other personnel you require.                   Depending upon machinery risk classification, some additional
                The meeting objective will be to qualify your bid technically,  end user in-house and/or independent third party design checks
              based on component experience, and to fully define scope of  may be required. In addition, separate vendor and sub-supplier
              supply and approve exceptions to specifications. If necessary,  machining,handlingandshippingcapabilityauditsmayberequired.
              the technical aspects for your equipment may change as a result
              of the meeting discussions. In addition to our (contractor)
                                                                   Typical compressor train pre-bid meeting
              equipment specialist the end user specialist ________ (or other  agenda
              assigned engineer) will participate in these meetings. We em-
              phasize that it is in your interest to bring the most qualified
              personnel to the meeting, since this will be the only technical  Please note that the following agenda will be followed for each
              meeting prior to the final bid.                       of the compressor trains being offered. Note: 1–2 days will be
                The following additional audits may be required as a result of  required for the meeting to review all details based on unit risk
              your bid details and the use of major sub-suppliers.  classification.
                ____________                                       1. Compressor experience review (vendor to include necessary
                                                                      reference charts, tables etc.)
                                                                       Casing experience and review of compressor layout drawing
                                                                       Impeller experience (flow and head coefficient)
                (The end user to identify sub-suppliers for manufacturing,
              handling and shipping audits based on vendor bid details)
                                                                       Individual impeller curve (location of rated point to
                At the conclusion of the meeting, all details will be summarized  impeller best efficiency point)
              and you will be asked to submit your priced proposal, in accor-    Impeller stress
              dance with the technical details, scope of supply and approved    Rotor response
              exceptions to specifications agreed to in the meeting. Your pro-    Stability analysis (if applicable)
              posal will be required in ________ weeks after the meeting.    Bearings – surface speed, load and experience
                                                                       Thrust balance
                (Normally 2 weeks but may be longer based on complexity of
                                                                       Seals – surface speed, balance forces and experience
              equipment offering and machinery risk classification.)
                                                                       Surge control and process control system
                The pre-bid meeting agenda is attached.            2. Steam turbine or motor experience review (vendor to
                                                                      include necessary reference charts, tables, etc.)
              Pre-bid procedure fact summary                           Turbine casing experience and review of layout drawing
                                                                       Stage nozzle and blade experience (profile, velocity ratio,
                                                                        BTU/stage)
              The following is a brief summary of the salient procedure facts:
                                                                       Blade attachment method and blade stresses
              1. Required personnel experience – experienced rotating    Campbell and Goodman diagram review
                 equipment specialists from contractor, supplier(s) and client    Rotor response

                                                                                                                13
   34   35   36   37   38   39   40   41   42   43   44