Page 44 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 44

Project Best Practices   Best Practice 1 .11


               Best
               Best Practice 1.11Practice 1.11Practice 1.11
               Best
               Conduct effective vendor coordination meetings (VCMs) to    Project schedule extensions resulting from engineering changes by
               confirm scope and design are in complete accordance    the EP&C (piping changes, foundation changes, etc.)
               with the purchase order.                              Project schedule extensions resulting from engineering changes by
                  Have the EP&C prepare the agenda, pass it by the end user team for  the vendor (machine changes due to process condition changes,
               review and issue to the vendor a minimum of 2 weeks prior to the  mechanical component changes arising from differences in
                                                                     interpretation of exceptions to specifications, etc.)
               meeting.
                                                                     Cost adders
                  Conduct the meeting in the vendor’s works and have it in the early
                                                                     Lack of trust between EP&C and vendor
               stages of the design engineering phase (approximately 6 weeks after
               order placement).
                  Be sure that the end user machinery specialist, an experienced  Benchmarks
               operator and maintenance engineer attend as a minimum.  Use of the above approach in all Critical Equipment Projects since
                                                                   1970 has resulted in ‘smooth, issue free projects’ without significant
               Lessons Learned                                     cost adders or schedule delays. VCM’s conducted in this best practice
               Poorly planned vendor coordination meetings (VCMs) and  format have been used in all projects that I have handled for the fol-
               absence of key individuals will result in cost adders and  lowing projects:
               delivery schedule extensions.                         Upstream oil and gas – offshore and onshore
                  If the VCM is not conducted properly, the following issues could    Refining
               arise:                                                Chemical
                                                                     Co-generation




              B.P. 1.11. Supporting Material                          Purpose – to confirm scope and design
                                                                      Design confirmation amount is proportional to the risk class
              The coordination meeting                                If there is any component inexperience, details must be finalized
                                                                      now!
                                                                      Location – vendor's shop
              After the order is placed, the coordination meeting is the first  Attendance by: vendor specialists, sub-supplier specialists,
              contact between the contractor, the end user and the vendor.  contractor specialists, end user specialists
              This meeting is usually held approximately 6 weeks after the  Timing – approximately 6 weeks after order
              order placement and should be held at the vendor’s shop.  Duration – 2–4 days based on complexity and risk class
                In my experience, the effectiveness of this meeting is sig-
              nificantly increased if the end user’s rotating equipment spe-  Fig 1.11.1   The VCM – key facts
              cialist and/or consultant, senior operator and maintenance
              engineer are in attendance. Depending on the project man-
              agement team, it may be necessary to ‘campaign’ for the at-  Agenda by vendor approved by contractor/end user
              tendance of these valuable people. There can be the suspicion  Agenda to be issued for review 2 weeks before meeting
              that incorporating these individuals will add additional cost to  Assure that all required design reviews are included
              the job. It is my strong opinion that the addition of these in-  Inform project team in advance of required attendance
              dividuals will reduce significantly the life cycle cost of the job  End user should take detailed minutes
              by incorporating lessons learned and best practices into the  Review all minutes and acceptance required by all parties, with
                                                                      action point responsibilities and required dates noted prior to
              job. Refer back to the pre-FEED phase of the job and note  adjournment
              that the same individuals were asked to contribute input to the
              job in this phase.
                My ‘best practice’ is to include a senior operator and main-  Fig 1.11.2   VCM agenda – key facts
              tenance man (millwright) in all phases of the project from pre-
              FEED up to and including the test phase. This ensures that all
              company ‘lessons learned’ are turned into ‘best practices’ for the  Review and confirm process conditions
                                                                      Review and confirm aero, thermo and mechanical design
              project.                                                Conduct any required design and/or manufacturing audits
                The key facts for the VCM (vendor coordination meeting)  Confirm all major connection locations
              are presented in Figure 1.11.1.                         Review machine and auxiliary layouts for maintenance
                Vendor coordination meeting key facts are shown in    accessibility
              Figure 1.11.2.                                          Review preliminary test agenda
                A VCM checklist is included in Figure 1.11.3 for your use,  Resolve any outstanding specification issues
              to ensure that all important facts are covered. Depending  Review vendor and sub-supplier QC procedures (there may be
              upon the risk class of the equipment, this may very well be the  a separate meeting for this activity)
              last chance for vendor engineering contact prior to the shop
              test phase.                                          Fig 1.11.3   VCM agenda checklist

                                                                                                                17
   39   40   41   42   43   44   45   46   47   48   49