Page 47 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 47

Be st Practice 1 .14          Project Best Practices


         Best Practice 1.14Practice 1.14Practice 1.14Practice 1.14
         Best
         Best
         Best
         Assure a FAT (Factory Acceptance Test) of maximum    Failure to conduct an effective FAT, from the end user’s per-
         effectiveness.                                     spective, will expose the end user to future safety and reliability
           Establish FAT test requirements in the job specifications and con-  issues.
         firm during the pre-award and coordination meetings.  My company has been involved with numerous site machinery re-
           Require the FAT agenda to be submitted for approval by the end  liability issues that have resulted from ineffective FATs.
         user a minimum of 2 months prior to the FAT date.
           Require a pre-test meeting the day before the first FAT with each  Benchmarks
         vendor.                                            The above approach has been used in critical equipment projects
           Assure that the FAT team consists of experienced machinery, op-  since the early 1990s, and has resulted in projects free of safety and
         erations and maintenance personnel as a minimum.   reliability issues, and without significant cost adders or schedule
           Require a post-test meeting to determine final acceptance and  delays.
         confirm the format of the format test report.

         Lessons Learned
         The FAT is the last chance to ensure that the equipment
         was designed correctly and operates with optimum safety
         and reliability!







       B.P. 1.14. Supporting Material                       phase. Yes, there certainly are many opportunities to ensure
                                                            equipment reliability during shop test, but there are also a lot of
                                                            potential lost opportunities if they are not justified to the project
       Testing phase                                        team early, during the pre-FEED phase of the project. The
                                                            potential lost shop test phase opportunities are noted in
       The testing phase is the last phase in terms of vendor and sub-  Figure 1.14.2.
       supplier design and manufacturing involvement in the project;
       and it is the last chance to ensure the optimum availability of the
       finished product.
          Remember that all of the equipment addressed in this
       section is most likely custom designed, and no matter how  The following opportunities will be lost if they are not justified at
       much accrued design and manufacturing experience is present,  project inception:
                                                                Possible full load test
       the possibility of some abnormality, hopefully a minor one, is  Unproven component tests
       high. Therefore, it is imperative that this phase be carefully  Attendance at test by plant personnel
       observed and witnessed by the end user team. Figure 1.14.1  Use of special tools
       lists some important facts surrounding this phase of the  Vendor permission for pictures
       project.                                                 Agreement that assigned vendor field service specialists will be
                                                                present for tests
                                                                Agreement that the instruction book is reviewed
                                                                Agreement for formal field construction meeting to clearly define
                                                                all vendor procedures from receipt of equipment on site to initial
        The shop test is an opportunity to:                     run in of equipment
           Confirm vendor proper design and manufacture
           To match field conditions
                                                            Fig 1.14.2   Potential lost test opportunities
           To witness assembly and disassembly using job special tools
           To have plant personnel observe test, assembly, etc. and take
           pictures for purposes of emergency field maintenance excellence
           Review the instruction book                        The success of the shop test depends on a good test plan that
           Have the assigned vendor field service engineer observe the
                                                            is reviewed by the end user and contractor and modified as
           equipment he will install                        requested well in advance of the test. Figure 1.14.3 presents
           Review all vendor field procedures
                                                            these facts.
                                                              I actually began my career in rotating equipment on the test
       Fig 1.14.1   The shop test                           floor. I can still remember how we would see the witnesses
                                                            come in with the intention of participating completely in the
                                                            entire test, only to leave for a long ‘test lunch’ an hour or so later.
          I have included a shop test checklist at the end of this section,  Why did this occur? Usually because the concerned end user
       which will be useful in planning and executing the shop test  and contractor witnesses did not have the opportunity to review

           20
   42   43   44   45   46   47   48   49   50   51   52