Page 45 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 45

Be st Practice 1 .12          Project Best Practices


         Best
         Best Practice 1.12Practice 1.12Practice 1.12
         Best
         Determine in the pre-bid project phase if and when design  conducted design audits were either not performed or conducted too
         audit meetings are required.                       late in the project.
           Determine the critical machinery risk class as soon as the project is
         announced, in the pre-feed phase, using the guidelines contained in  Benchmarks
         the supporting material section of this B.P. It may be necessary to use  The above approach has been used in critical equipment projects since
         design audits in the pre-feed phase as a means of vendor acceptability  1990, and particularly since 2000 when MEGA projects became
         screening.                                         common in the industry. This approach has resulted in projects free of
           Determine if vendor sub-supplier audits are required (carefully  safety and reliability issues, without significant cost adders or schedule
         review ‘new international country sources’– China, Middle East, etc.).  delays. Design audits were performed in compressor trains for the
         The machinery industry has recently experienced poor quality sub-  following recent projects:
         supplier work from ‘new countries’ entering into sub-supplier work.    Refinery hydrocracker recycle compressor
                                                              LNG mixed refrigerant compressor
         Lessons Learned                                      Methanol MAC and BAC air separation train
         Failure to conduct design audits at the proper time in    Ethylene refrigeration compressor
         a project can lead to significant start-up delays, and life-  The anticipated revenue savings from properly timed and conducted
         long machinery safety and/or reliability problems.  design audits can easily reach $60m, or much greater if based on a $1m
           Since 1990 FAI has been involved with many field troubleshooting  per-day-plant. Design problems that are not determined during an audit
         assignments (RCFAs). These were required because properly  can easily cause field delays in excess of two months.






       B.P. 1.12. Supporting Material

       Design and manufacturing audits                          Machining capabilities (max, size capability)
                                                                Balancing capabilities (Low speed and/or high speed, max rotor
                                                                size)
       The need for design and manufacturing audits, as previously  Size of assembly area
       stated, depends on the equipment risk class, vendor and sub-  Shop load status
       supplier design, and manufacturing experience level. These audits  Testing capabilities (gas test, full load test, power limits)
       can be conducted at any phase of the project, but the sooner the  Handling capabilities (max lift, laydown area)
       better. Prototype equipment requires that audits be conducted  Shipping capabilities
       during the pre-FEED or FEED phase of the project. Today, most
       projects are defined as MEGA projects, since the process units are  Fig 1.12.2   Manufacturing audit guidelines
       the largest size ever built and most probably will incorporate single
       equipment trains that are prototype in nature. Therefore, many
       projects require that design audits (pre-screening) should be  Table 1.12.1 Suggested design audit activity
       conducted as soon as the project starts. Planning and conducting
       effective supplier design and manufacturing audits requires pre-  Suggested design audit activity
       planning and a significant amount of work, but it is certainly worth
       the effort in terms of increased profits and reduced project  1. Risk type          1    2     3    4
       schedule. These salient points are noted in Figure 1.12.1.  2. Design checks
          When supplier or sub-supplier manufacturing audits are re-     ■  Aero-dynamic   X   X     ?    *
       quired, suggested action is shown in Figure 1.12.2.      ■  Thermodynamic          X    X     ?    *
                                                                ■ Rotor response          X    X     ?    *
          In Table 1.12.1 I have presented a suggested list of what the     ■   Stability analysis (if applicable)   X   X   ?   *
       design audit should include, depending on the risk classification.     ■  Seal balance   X   X   ?   *
                                                                ■  Thrust balance         X    X     ?    *
                                                                ■  Bearing loading        X    X     ?    *
                                                                ■   Train lateral analysis   X   X   ?    *
           Detailed agenda, well in advance                     ■   Torsional analysis (if applicable)   X   X   ?   *
           Design audit at vendor's offices with follow-up at end user’s     ■   Transient torsional (if req’d)   X   X   ?   *
           offices                                               ■   Control system simulations   X   X   X   X
           Manufacturing audit at vendor's and/or sub-supplier’s plants     ■   System layout – accessibility   X   X   X   X
           End user specialists must participate
           Conduct preliminary end user in-house checks prior to the design  Key    1 = Prototype      X = Required
           audit if possible                                       2 = Multiple component inexperience   ? = Optional
                                                                   3 = Single component inexperience    * = Not required
                                                                   4 = Proven experience for all components.
       Fig 1.12.1   Vendor audit requirements

           18
   40   41   42   43   44   45   46   47   48   49   50