Project Best Practices   Best Practice 1 .14



               3. Shop test activity

               Review and understand test agenda prior to test
               Immediately prior to test meet with assigned test engineer to:
               , Review schedule of events
               , Designate a team leader
               , Confirm test team leader will be notified prior to each event
               , ‘Walk’ test set-up to identify each instrumented point
               , Confirm calibration of each test instrument
               , Obtain documents for data reduction check – if applicable
               (flow meter equations, gas data, etc.)
               During test
               Note: coordinate with test personnel to avoid interference
               , Review ‘as measured’ raw data for consistency
               , ‘Walk’ equipment – look for leaks, contract instrument, piping
               and baseplate vibration, etc.
               , Use test team effectively – assign a station to each individual
               , Ask all questions now, not later, while an opportunity exists to
               correct the problem
               , Check vendor’s data reduction for rated point – if applicable
               After test
               , Inspect all components as required by the test agenda
               (bearings, seals, labyrinths, RTD wires, etc.)
               , Review data reduction of performance data corrected to
               guarantee conditions
               , Review – all mechanical test data
               , Generate list of action (if applicable) prior to acceptance of test
               , Approve or reject