Project Best Practices   Best Practice 1 .13
                After conducting the appropriate audits, prompt follow-up
              regarding any action items is required to confirm the acceptance  Lube/seal oil system
              of the supplier and/or sub-suppliers, and to maintain the project  1. Introductions
              schedule. Figure 1.12.3 presents these facts.         2. Purpose of meeting
                                                                       2.1 Review study results, past modifications/failures and
                                                                          recommendations to assist client in resolving seal oil
                                                                          delta pressure trips on the subject compressor.
                                                                          2.1.1 Supply client with recommendations, modifications
                  Prepare an executive summary of conclusions                 required and cost and delivery.
                  Immediately present to the project team for approval  3. Results of studies performed in the field
                  Inform vendors of results                            3.1 Client field reliability study
                  Prepare vendor follow up meeting agenda              3.2 Vendor engineering study
                    Note action required and follow up as required to maintain  4. Review seal design and requirements
               project schedule                                        4.1 Review seal components and function
                                                                          4.1.1  Upgrades?
                                                                          4.1.2  Modifications?
              Fig 1.12.3   Design audit summary and follow up action  5. Review seal oil system component design
                                                                       5.1 Sizing of components (pumps, coolers, filters, reservoir, etc.)
                                                                       5.2 Review valve selection and sizing (including Cv)
                After completion of the required audits, regardless of the  5.3 Review control system
              project phase in which they were conducted, follow-up docu-  5.3.1  Upgrades?
                                                                          5.3.2  Modifications?
              ment review is essential to confirm that all stated design and  6. Review comments to seal oil system component sizing study
              manufacturing requirements are met.                      6.1 List recommendations
                In Figure 1.12.4, I have presented a typical design audit  6.1.1  Feasibility and reliability issues
              meeting agenda to resolve a long term problem with a com-  7. Review final recommendations and feasibility
              pressor seal oil system. Always remember to send agendas well  7.1 Assign tasks and schedules
              in advance to allow the vendor sufficient time to prepare the  7.2 Create final timeline up to delivery of parts and installation
                                                                    8. Conclusion
              required material.
                                                                   Fig 1.12.4   Design audit agenda








               Best
               Best
               Best Practice 1.13Practice 1.13Practice 1.13
               Timely vendor and EP&C document review.               I have been involved in projects where the scheduled plant per-
                  Finalize document review times in the pre-feed phase of the project,  sonnel document review response time has been very unrealistic. This
               and ensure they are realistic, and will enable comments from plant site  has caused important plant review comments to not be incorporated in
               personnel to be incorporated.                       the machinery design, which has resulted in reliability issues in the field
                  Review all documents completely, and watch out for vendor and/or  that delayed plant start-up and could have been avoided.
               EP&C ‘cut and paste’ documents that are from other projects in error or
               are generic in nature.                              Benchmarks
                  Follow up by reviewing the next issue of the document to ensure  I have used the above approach in all critical equipment projects since
               that your comments have been incorporated.          1975. This approach has resulted in safety and reliability ‘issue free’
                                                                   projects, without significant cost adders or schedule delays.
               Lessons Learned
               Inefficient vendor and EP&C document reviews will cause
               delivery delays and possible field start-up delays.



              B.P. 1.13. Supporting Material
                                                                      Assure that required review time frames are realistic and then
                                                                      meet them!
              Document review                                         Thoroughly review all items
                                                                      Question all required items and follow-up
              It goes without saying that document review should definitely  Be especially careful in the final phases of the project to ensure
                                                                      that all required vendor changes have been made
              be timely, within the project schedule, and accurate. However,
              in addition there are other pertinent points, which are presented
              in Figure 1.13.1.                                    Fig 1.13.1   Effective document review considerations