                    Other aspects that should be included are protective devices, measurement detectors, terminal
              blocks, segregation of circuits and terminals, voltage surge suppression, skid construction, floor
              frames, lifting eyes, jacking points, earthing bosses, indicating devices, control switches, automatic
              voltage regulators, exciters, detachable panels and doors, forced cooling, shaft bearings and seals,
              lubrication systems, anti-condensation heaters, noise levels, labelling and nameplates, painting etc.
              Some of these may be efficiently included in the data sheet.


              19.2.8 Inspection and Testing

              Inspection and testing of the purchased equipment is one of the most important tasks in the engineering
              of a project. Its importance is sometimes underestimated. The first serious tests that the purchaser
              will witness are those in the factory where the equipment is assembled. These tests will also include
              a physical inspection of the equipment.
                    It is therefore important to state clearly in the specification what inspection and testing will
              be required and, where appropriate, what are the acceptable limits of the results. Most tests required
              in the oil industry are covered in international specifications and these can be used as references.
              However, not all those in the reference documents need to be carried out in all cases. It is therefore
              prudent to state the requirements in the project specification in one or more of the following methods:

              • Write a detailed description of exactly what is required, including the limits that are acceptable and
                the form in which the results should be reported. This method ensures a ‘self-contained’ approach
                that is very beneficial during the actual testing operation. Often time is limited to perform tests and
                to have all the requirements to hand without having to search through related documents enables
                the work to be completed very efficiently.
              • Quote the exact clause numbers and sub-section headings in the reference documents for the
                particular tests to be performed. This may be less efficient when the time of the tests becomes due,
                especially if the reference documents are not easily to hand. If a statement is made such as ‘the
                switchgear shall be tested in accordance with the XYZ-123 international standard’ and no other
                clarification is included, then many debates can arise at the time of testing.

                    Whichever method is used it should be carefully checked by a quality assurance department
              before the specification is approved for purchasing the equipment.

                    Some types of equipment require ‘production tests’, ‘type tests’, ‘performance tests’, ‘routine
              tests’, ‘abbreviated tests’ or ‘special tests’, or a combination of these tests. The subtitles are sometimes
              used with different meanings. Production tests are required for complex equipment such as high-
              voltage generators and motors, and these tests are performed in the factory before the complete unit
              is assembled. For example the rotors are balanced without the stator, air-to-water heat exchanges
              can be tested to withstand hydraulic pressure, winding insulation and individual coil insulation can
              be tested.
                    Type tests are performed on one from a group of identical units. These tests are comprehensive
              and some of which are usually only performed once in the life span of the equipment.
                    If the equipment is a standard product of the manufacturer for which existing certificates can
              show that a type test has previously been carried out, then the purchaser may wish to accept the
              certificate without repeating the test. This is largely a matter of choice than necessity.