Page 80 - How To Implement Lean Manufacturing
P. 80

Lean Manufacturing Simplified     61


                    nearly all the 20 Lean tools require an understanding of, and reduction of, variation to
                    work.
                    Stability

                    OEE  OEE stands for Overall Equipment Effectiveness and is the primary measure of
                    production effectiveness. It can be used for value stream or individual work station
                    performance evaluation. Good value stream OEE is one of the key precursors to the
                    implementation of Lean and is the product of three important operational parameters.
                    These are:
                        •  Equipment availability
                        •  Quality yield
                        •  Cycle-time performance
                       To calculate OEE, you will need five parameters. First is the planned production
                    time for the line. Second is the unplanned line downtime. Third is the line cycle time, or
                    cycle time, of the bottleneck. Fourth is the total production including scrap, and fifth is
                    the total amount of salable product. Let’s say we have the following data:
                        •  Planned production time is 20.5 hours. It is 24 hours less 1 hour per shift for
                           lunch and breaks, and less one-half hour for planned preventive maintenance.
                        •  Unscheduled downtime was 1.5 hours.
                        •  Design cycle time is 30 seconds per piece.
                        •  Actual total production was 2020 pieces with 50 rejects, yielding 1970 pieces of
                           salable product. This then allows us to calculate:
                           •  Availability = Total uptime divided by total planned uptime = A = (20.5 – 1.5)/
                             20.5 = 0.927
                           •  Quality Yield = The total of salable production units divided by the total
                             production = Q = 1970/2020 = 0.975
                           •  C/T Performance = Total units produced, good and bad, divided by the volume,
                             which should have been produced during the actual uptime at the design
                             cycle time = P = 2020/[(20.5 – 1.5) × (3600/30)] = 0.886
                           •  OEE = A × Q × P = 0.801

                       This is a way to express how our production facility is performing, and then priori-
                    tize our problems and allocate our resources. In this example, OEE is 80 percent. The
                    losses can be stated as about 2.5 percent due to quality issues, 7.3 percent losses due to
                    availability issues, either materials delivery or machinery downtime, and we are losing
                    11.4 percent due to the line not performing at the design cycle time. It is a very good
                    picture of plant performance and allows management to focus on the appropriate goals
                    for improvement.

                    MSA  MSA stands for measurement system analysis. It is the statistical calculation
                    of the variation in the measurement system and applies to both attribute and vari-
                    ables data. MSA must be done on all measurement systems. The most common use
                    of MSA is as a precursor to doing a capability study on a product characteristic or a
   75   76   77   78   79   80   81   82   83   84   85