Page 95 - How To Implement Lean Manufacturing
P. 95

76    Cha pte r  F i v e


                        •  Even if they started jobs with plenty of time, they always seemed to need
                           overtime to complete jobs. Even after working overtime, 35 percent of the jobs
                           had unscheduled expedited freight charges that cut deeply into profit
                           margins.
                       We took a plant tour and it was obvious that Lean techniques were something they
                    desperately needed. Around their problems we designed a four-day training curricu-
                    lum in Lean. During the class, we also did a group project. The task was to apply the
                    Lean principles to one of their manufacturing applications. In the class they got so
                    excited about what we had accomplished on paper, they wanted to apply it to the floor.
                    They extended our contract and we went to the floor.

                    The Product
                    This plant was a metal fabricator. The product they had chosen to Lean out was a junc-
                    tion box used in the telecommunication industry. The external dimensions of the box
                    were 36 inches high by 24 inches wide and 8 inches deep. It was made from 12 gauge
                    precoated steel. In addition to the 80 rivets and 40 screws per assembly, there were
                    22 items on the bill of materials

                    The Process

                    The CNC Punch Press—Turret
                    The process consisted of using a Computer Numerical Control (CNC) punch press to
                    stamp out a topside assembly consisting of the top and seven other smaller parts. The
                    large sheets were manually loaded onto the punch press; each sheet made five assem-
                    blies. While it was cycling, the operator would separate the prior sheet, remove the
                    protective coating, segregate the parts, and load them into containers to be transported
                    to the deburring operation. After 100 assemblies were completed, the operator would
                    transport the production to deburring, change the setup, and produce the bottom-side
                    assembly. The bottom-side assembly consisted of the bottom and four other smaller
                    parts. These parts were handled the same as the topside assembly, with protective coat-
                    ing removal, segregation, and placement into containers for transportation to deburr-
                    ing. After 100 assemblies had been produced, these too were transported to deburring
                    and the operator would make a changeover to his next product. The machine cycle time
                    was ten minutes, or two minutes per assembly, for both the top and bottom-side assem-
                    blies. The changeover time for this product was 36 minutes.

                    Deburring
                    The work in process (WIP) from the Turret was then transported to deburring. With
                    automatic deburring machines, the cycle time per assembly was 36 seconds and no
                    changeovers were required. The deburring operator was very lightly loaded. He would
                    deburr a batch of 100 topside assemblies and transport them to the Press Break for
                    bending. He would wait for the bottom-side assembly to arrive and then deburr and
                    transport these to the Press Break.
                    The Press Break
                    At the Press Break, the operator would bend the pieces to the assembly and although
                    there were more pieces and more bends to the topside assembly, both the topside batch
   90   91   92   93   94   95   96   97   98   99   100