Page 244 - Hydrocarbon Exploration and Production Second Edition
P. 244

Well Dynamic Behaviour                                                231


             represents a range of scenarios, aimed at determining the optimum development plan
             (the one with the highest NPV, as defined in Chapter 14).
                At the stage of field development planning, reservoir simulation would normally
             be used to generate production profiles and well requirements for a number of
             subsurface development options, for each of which different surface development
             options would be evaluated and costs estimated.




                  10.2. Fluid Flow Near the Wellbore

                  The pressure drop around the wellbore of a vertical producing well is
             described in the simplest case by the following profile of fluid pressure against radial
             distance from the well (Figure 10.2).
                The difference between the flowing wellbore pressure (P wf ) and the average
             reservoir pressure ( ¯ P) is the pressure drawdown (DP DD )

                                                            ðpsiÞ or ðbarÞ
                            Pressure drawdown DP DD ¼ ¯ P   P wf
                The relationship between the flowrate (Q) towards the well and the pressure
             drawdown is approximately linear for an undersaturated fluid (i.e. a fluid above the

                                            Cross-section

                                                well

                               r e       r
                                                    r w              P e

                             P                                       P

                                Δ P DD

                                          P wf














                                             Plan View
             Figure 10.2  Pressure distribution around the wellbore.