Page 206 -
P. 206

188       CHAPTER 6  The Production Process



                                          manufacturing and therefore are not discussed in this chapter. There are many
                                          other types of task lists. We will discuss some of them in later chapters in the
                                          context of other processes. Others are beyond the scope of this book. Finally,
                                          standard value keys are used to assign standard or planned values for the
                                          normal time elements—that is, the activities that consume time—associated
                                          with the work center. Typical time elements are setup time, processing time
                                          (machine and labor), and teardown time. The keys utilize specifi c formulas to
                                          calculate how much time must be allotted for each of these elements.
                                               Work center data also include default values for operations performed
                                          at the work center. Examples of default values are control keys and wage
                                          data. Control keys specify how an operation or a suboperation is scheduled,
                                          how costs will be calculated, and how operations will be confi rmed once they
                                          are completed in the work center. For example, a control key can indicate
                                          that confi rmation of an operation is required and must be printed before the
                                          next operation can be performed. Wage data are associated with processes in
                                          human capital management, such as payroll.
                                               Available capacity defi nes how much work can be performed at the
                                          work center during a specifi ed time. A work center can include more than one
                                          resource or capacity, such as labor and machine. In this case, the scheduling
                                          basis determines the specifi c capacity to be utilized for production.
                                               A work center is associated with a cost center. Recall from Chapter 3 that
                                          a cost center is a container or bucket that accumulates costs that are then allo-
                                          cated or further processed by management accounting processes. Costs associ-
                                          ated with operations completed in a work center are calculated using formulas
                                          that utilize the costs and the standard values associated with each activity type
                                          (e.g., setup, labor, and machine).
                                               GBI has three work centers, as illustrated in Figure 6-7 and Figure 6-8.
                                          Figure 6-7 shows the layout of the production facility in Dallas. It identifi es the
                                          three work centers (ASSY1000, INSP1000, and PACK1000) and the four storage
                                          locations (RM00, FG00, SF00, and MI00). All three work centers are associ-
                                          ated with one cost center, the production cost center (NAPR1000).
                                               Figure 6-8 provides details of the three work centers.  ASSY1000 is
                                          the assembly work center. It has 8 hours of labor capacity. Labor is used to
                                          complete three operations—stage or prepare materials, construct the wheel
                                          assembly, and assemble the fi nished bike. INSP1000 is the inspection work
                                          center. Here the bike is placed on a machine that tests its suspension and bal-
                                          ance. Meanwhile, the employee visually inspects the entire bike, checking for
                                          defects. In contrast to the assembly work center, then, the inspection work
                                          center utilizes both labor and machine capacity. Once testing has been com-
                                          pleted, the bike is disassembled into the frame assembly and the wheel assem-
                                          blies. These components are then packed separately in the fi nal work center
                                          (PACK1000), which, like assembly, involves only labor. The fi nal assembly is
                                          typically completed at the retailer’s location or by the customer after he or she
                                          purchases the bike.

















                                                                                                                 31/01/11   6:40 AM
          CH006.indd   188
          CH006.indd   188                                                                                       31/01/11   6:40 AM
   201   202   203   204   205   206   207   208   209   210   211