Master Data 193
Figure 6-11: Routings and work centers
Figure 6-12: Routing for deluxe touring wheel assembly
the 50 wheels assemblies into storage. Because these operations are performed
manually, they do not involve any setup time. Consequently, all the time spent
on these operations is labor time. Overall, it takes 160 minutes (5 50*3 5)
to assemble 50 wheels, an average of 3.2 minutes per wheel.
Figure 6-13 presents the routing for the deluxe touring bike. In con-
trast to the wheel assembly, this routing includes 11 steps. Further, the opera-
tions are completed in three different work centers: ASSY1000, INSP1000, and
PACK1000. Finally, one operation—#80, Test bike—includes a setup time of
2 minutes. This is the amount of time it takes to place the fully assembled bike