Page 138 - Machinery Component Maintenance
P. 138

Machinery Founddons and  Grouting   121

                                        Epoxy Grout Placement

                    The pump baseplate is ready for grouting after the following last min-
                  ute checks are made:
                      Baseplate under  surface is free of  oil,  scale, dirt,  or moisture and
                      sealed with a coating of unfilled  epoxy grout.
                      Concrete surface is clean. free of oil, dirt, and moisture. It is sealed
                      with a coating of unfilled epoxy grout.
                      Anchor bolt  sleeves are filled with non-bonding material.
                      Exposed surfaces of anchor bolts are covered with sealant or wax.
                      Jack screws are lubricated  for easy removal.
                      Circular steel plates are under each jack-screw  point.
                      Vent  holes are in correct  locations and unobstructed.
                    0  Forms in contact with grout are properly waxed (three coats).
                      Grouting materials  are  in  unopened containers,  dry,  and  stored  at
                      70°F to 80°F for 24 hours prior to placement.
                    0 Sufficient quantities of  grout  materials are on  hand  at  site to com-
                      plete work.  (Add 25 percent to calculated  grout requirement.)
                    Epoxy grouts have a narrow temperature range for mixing and place-
                   ment. This range is from 50°F to 90°F for best pot life, flowability, and
                  curing. Can epoxy grout be poured at temperatures below or above these
                   limits? The answer is yes, but special procedures must be followed and
                   the grout manufacturer should be consulted. Low temperature accelera-
                  tors can be added for cold weather pours with the foundation and base-
                   plate covered and heated. In parts of the world, the problem is with tem-
                   peratures  above 95°F. Consider  storing epoxy  grout  and  aggregate in
                   air-conditioned offices for 48 hours to increase the pot life on hot days. In
                   hot weather. construct temporary  shelters over the baseplate to provide
                   shade 24 hours before and 48 hours after the grout placement. It is a good
                   practice to rope off a work area in congested construction sites to set up
                   the grouting operation. Grouting material and tools should be located in-
                   side the roped-off area just before the job starts.
                    With temperature-conditioned grout at the pump site and all the check-
                   list items completed, it is time to mix the grout. There are two ways to
                   mix the grout:
                      In a wheelbarrow with a mortar mixing hoc.
                      In a motorized  mortar mixer.

                   Both methods work well, but for a large grout job (10 units or more) the
                   motorized mixer should be used. If the hand-mixing method is used, have
                   two wheelbarrows and stagger their mixing sequence to provide a contin-
                   uous  supply of  grout to the people  making  the pour.  The hand-mixing
   133   134   135   136   137   138   139   140   141   142   143