Page 63 - Mathematical Models and Algorithms for Power System Optimization
P. 63

Optimization of Annual Generator Maintenance Scheduling 53

               A GMS problem should have the following characteristics: the maintenance time for full or
               partial maintenance can be different. Each unit’s maintenance can be performed multiple
               times within a given interval. When developing a GMS, the proposed ES can determine the
               priority.

               The objective function should consider both the maximizing reserve margin and minimizing
               production cost. The constraints should consider the maximum area maintenance capability, the
               reserve margin of generators, the maintenance window cycle, continuous maintenance
               conditions, and available manpower.
               The GMS problem mentioned earlier requires a lengthy solution time and large computing
               memory. The existing programming techniques cannot be directly applied. However, a dispatch
               engineer with GMS experience may potentially be able to solve the GMS problem. Using their
               experience, an ES can be constructed. But the prototype ES can only be used to solve the GMS
               problem of a particular system. The generalized ES proposed in this chapter can be applied to
               GMS problems of different power systems.

               In view of the large differences in the number of generators and the capacity of each
               power plant in each region, maintenance periods vary in length; some are shorter
               (more than 7 days), whereas some are much longer (more than 35 days). Some
               generators must be maintained within a given time, whereas others can be handled
               in a flexible way. There are many necessary conditions and constraints to be
               considered in the GMS problem. The following briefly introduces the modeling
               ideas of GMS.



               3.2.1 Way of Handling Unit Maintenance Intervals


               A GMS problem can divide the units in need of maintenance into two categories based on
               maintenance time: fixed maintenance and flexible maintenance.

               (1) Fixed maintenance refers to the unit being maintained or the unit that needs to be
                    maintained at the specified time. Its maintenance capacity must be reserved in the
                    GMS. For those units that have shut down due to a fault, the maintenance should
                    obviously be classified as a fixed maintenance. Therefore, the fixed maintenance
                    arrangement can also be used to simplify the GMS in some cases.
               (2) Flexible maintenance refers to the units that are not included in the fixed maintenance,
                    that is, the units whose maintenance start time can be flexibly arranged and
                    optimized to some extent. In the case of the current general lack of electricity in the power
                    grid, the objective function of GMS in the flexible maintenance can be set to
                    maximize the reserve margin of the system for the general system, and to minimize
                    the production and maintenance costs of the system with adequate reserve margin.
   58   59   60   61   62   63   64   65   66   67   68