Page 179 - Orlicky's Material Requirements Planning
P. 179

158                                                                 PART 2   Concepts


             When the planned orders are eventually released, the full quantity, including the
        scrap allowance, should be shown as on order. This quantity then would be reduced as
        and if scrap transactions are posted to the record. The practice of including scrap-
        allowance quantities in the item’s gross requirements (in order to display the projected
        on-hand quantities as they are expected to be after scrap) is unsound because it distorts
        the fundamental relationship of parent planned-order quantity to the component item’s
        gross requirements quantity. Furthermore, whether scrap actually will occur is uncertain.
        Until it does occur, the MRP system should project the item’s status as though it will not
        occur.
             Another constraint that can be imposed on the lot-sizing algorithm is the require-
        ment that a given item be ordered in multiples of some number. This may be dictated by
        considerations of process (e.g., so many pieces constitute a Blanchard grinder load or so
        many bars of steel are fed to a bar lathe simultaneously), packaging (e.g., 12 pieces in a
        carton), and so on. The lot size yielded by the lot-sizing algorithm is, in these cases,
        increased to the nearest multiple specified.
             Raw material cutting factors represent another adjustment to lot size that it is desir-
        able to make in certain instances. The lot-sizing algorithm, unaware of the form in which
        raw material (from which the item in question will be made) comes, may generate a
        quantity that would create problems in cutting this material. For example, if a certain size
        of sheet metal is cut into nine pieces in the manufacture of a given inventory item, a lot
        size of 30 will result in either an odd size of raw material being left over or, more likely,
        the shear operator cutting the four sheets into 36 pieces. This then will become the actu-
        al quantity on order, as opposed to the 30 on order shown by the system.
             In cases where more than one type of adjustment is to be made to the order quanti-
        ty for a given item, the several adjustments are made consecutively in a logical sequence.
        For example, if the lot-sizing technique yields a quantity of, say, 173, which is equivalent
        to five periods’ requirements, and the item is subject to a three-period ceiling, scrap
        allowance, and cutting constraint (20 pieces per unit of raw material), the “raw” quanti-
        ty of 173 would be adjusted as follows:
             Raw order quantity:                               173
             Reduce to three periods’ requirements:            121
             Add scrap allowance:                               11
             Total:                                            132
             Increase to nearest multiple of 20:                 8
             Adjusted order quantity:                          140

             Scrap allowances, multiples, and cutting factors tend to create an inventory excess.
        This excess, however, is subsequently applied by the MRP system against later gross
        requirements. At any point in time, there exists a slight inventory excess, but it does not
        accumulate.
   174   175   176   177   178   179   180   181   182   183   184