Page 388 - Orlicky's Material Requirements Planning
P. 388

CHAPTER 21   Historical Context                                                 367


             The basic formula is

                                           Quantity       2AS
                                                          iC

        where A is annual usage in units, S is ordering costs, i is annual inventory carrying cost
        rate as a decimal, and C is unit cost.
             The economic order quantity (EOQ) turns out to be a poor ordering quantity in the
        typical manufacturing demand environment. The EOQ equation is totally insensitive to the
        timing of actual, discrete demands (requirements) arising during the period that the EOQ
        is intended to cover following its arrival in stock. Once future requirements for an inven-
        tory item are precisely determined and positioned along a time axis, it can be seen that the
        square-root approach in the EOQ calculation does nothing to balance the lot size against
        either the timing or the quantity of actual requirements. For example, demand for an item
        over a 10-week period may be determined in advance to be, by week, 20-0-20-0-0-0-0-0-20-
        0. The EOQ for this item may turn out to be 50, more than needed to cover the first three
        weeks’ requirements but not enough to cover the next requirement in the ninth week. The
        “remnant”‘ of 10 pieces will be carried for eight weeks without any purpose. Note that the
        EOQ still would be 50 if the 10-week demand were 20-0-40-0-0-0-0-0-0-0 or 20-0-0-0-0-0-0-
        0-0-40. In the first instance, the EOQ would fail to cover the first three weeks’ requirements,
        and in the second, the excess 30 pieces would be carried for nine weeks without being able
        to satisfy the requirements of the tenth week. In any of these cases, the EOQ is determined
        solely on the basis of setup cost, unit cost, carrying cost, and annual usage. The derivation
        of the EOQ formula rests squarely on a basic assumption of uniform demand in small incre-
        ments of the replenishment quantity, that is, gradual inventory depletion at a steady rate,
        which then allows the carrying cost to be calculated for an “average” inventory of one-half
        the order quantity. This basic assumption is grossly unrealistic vis-à-vis a manufacturing
        inventory and therefore fatal to the validity of the technique.
             The stock replenishment, order-point, and order-quantity techniques dominated the
        pre-MRP world in both actual practice and the inventory control literature. The reason for
        this is historical. The field had been conditioned in favor of the philosophy expressed by
        these techniques because the pioneering theoretical work in inventory control generally
        was confined to the areas of order point and order quantity. This work had been stimu-
        lated by the fact that problems of order point and order quantity lend themselves to the
        application of mathematical statistical methods that have been known and readily avail-
        able for quite some time. The inventory control problem was perceived as being essen-
        tially mathematical rather than one of massive data handling and data manipulation, the
        means for which simply did not exist before the computer and MRP.


               Analysis and Categorization of Inventory by Function
        The fact that the chronic problems of manufacturing inventory management now can be
        solved, however, is due not to better mathematics but to better data processing and com-
   383   384   385   386   387   388   389   390   391   392   393