Page 496 - Orlicky's Material Requirements Planning
P. 496

CHAPTER 27      Highly Visible and Collaborative Execution                      473


           FIGURE 27-25

           All order activity for Part PPZ with projected on-hand position.
          Part #: PPZ           PBS: SOWD in 6 Days                          Today’s Date: 5/20
          Order #     Quantity   Projected   Request      Promise   Status
          MO 531-99       –10         45       5/22        5/22     Unreleased
          MO 532-10       –10         35       5/23        5/23     Unreleased
          MO 532-32       –40         –5       5/24        5/24     Unreleased
          PO 625-71        30         25       5/25        5/25     In process at supplier
          PO 626-05        25         50       5/29        5/29     In process at supplier


             ■ A planner/scheduler could push the release of the parent order back. In this case,
                the parent is buffered. The planner/scheduler should check the buffer status of
                the parent item before pushing the date back. If the buffer is in an acceptable posi-
                tion (from both available stock and on-hand perspectives), then pushing the
                order back one to two days may be a good option. This is one of the benefits to
                having a buffer at the parent—the absorption of variability from both supply and
                demand.
             ■ A planner/scheduler could amend the quantity of the demand order to a lower
                amount (five fewer pieces). In this case, this might work because the parent is a
                buffered item. As in the preceding case, the planner/scheduler should check the
                buffer status of the parent item before doing this. If the buffer is in an acceptable
                position (from both available stock and on-hand perspectives), then the quantity
                change can be done with little to no risk to the system. Once again, this is one of
                the benefits to having buffers—the absorption of variability from both supply
                and demand.
             ■ A planner/schedule could look to substitute an alternate material if this is an
                option.
             Regardless of what action is taken, there needs to be a defined process to resolve
        MSAs. Attempts to rectify the MSA can involve changes to either component orders or
        parent demand requirements or possibly some combination of both. Frequently, these
        components will be under the control of different personnel and/or departments. The
        MSA is meant to focus the relevant personnel to collaborate and find the best potential
        solution together.
             Continuing with the example in Figure 27-24, there is an additional MSA. In this
        case, the MSA is between a nonbuffered parent (Part FPS) and a non-buffered component
        (Part PPY). The “NB” in the “Order Type” column stands for non-buffered. The synchro-
        nization problem is to happen eight days from today. It occurs because the component’s
        supply-order promise date is now five days behind the planned release of the parent
        demand order. The quantity shortage is for the entire order; both parts are non-buffered.
        In this case, there will be a different, albeit more limited, set of options because neither of
        the parts is buffered.
   491   492   493   494   495   496   497   498   499   500   501