Page 335 - Petroleum Geology
P. 335

305

               Drilling  in  Trinidad  and  the  US. Gulf  Coast  around  1940 led  to some
             blowouts in which the pore pressures apparently greatly exceeded  anything
             that  could  reasonably  be explained in terms of  a normal hydrostatic water
             regime. These difficulties were encountered more widely by  the 1950s  - in
             Brunei,  Indonesia,  Burma,  for  example,  and  then  the  Niger  delta.  In  the
             U.S.S.R.  similar  experiences occurred  (see  Fertl,  1976, p.  334). Abnormal
            these pressures might be, but they were becoming very common.
              Typically,  the  experience  was  this:  having drilled  1.5 km  or so without
            difficulty, penetration  rate increased and soon afterwards the mud  was ob-
            served to be flowing from the well at a greater rate over the shale shaker, and
            the  mud  tanks  started  filling up.  When  drilling  was  stopped  and  the mud
            pumps  shut down,  mud  continued  to flow  from  the  well  at an increasing
            rate, so the blowout preventers were closed. It was commonly found that mud
            of  specific gravity 1.5-1.8  was required  to control the influx into the bore-
            hole.  If  drilling was continued, the specific gravity of the mud had to be con-
            tinually  increased  until  the  practical  limit  of  about  2.2  was  reached.  The
            borehole then had to be abandoned.  Such heavy  muds were needed to con-
            trol pressures that approached  those of  the total overburden, corresponding
            to specific gravities of 2.2-2.4.
              In some boreholes, the mudstone tended to squeeze into the hole, making
            it tight and tending to stick the tools. These beds were called “heaving shales”.
            They  showed up on caliper logs, and it was quite common to find that one
            could not get back to bottom after a round trip without reaming or redrilling
            the last part.
              If  there  was  much  open  hole  when  the mudweight  was increased, there
            was an increased tendency for the pipe to stick - not on bottom,  but well
            up the hole in the normally pressured part of  the sequence. This was called
            “wall-sticking”. The excess pressure of the mud over the formation fluids held
            the drill pipe to the wall  of  the hole with  considerable force. (See Thomeer
            and Bottema, 1961, for some histories of drilling abnormal pressures.)
              The  practical  solution  of  these  problems  is not  without interest.  In the
            mid-1950s it was found that the best manner of drilling in areas in which ab-
            normal pressures were expected was to use the lightest possible mud from the
            beginning. This was a remarkable conclusion in the face of the normal prac-
            tice of weighting up the mud in anticipation of abnormal pressures. With lighter
            mud, the normally pressured  part  of  the hole drilled faster; and careful con-
            trol  of  the  drilling  parameters  resulted  in early detection of  the increasing
            drilling rate (called the “drilling break”).
              As  soon as the drilling break  was detected, the bit was pulled back above
            where  the  drilling  break  started, pumps were stopped and the mud-level in
           the borehole watched.  The mud  was then circulated “bottoms up”.  It could
            thus be determined if  there was influx into the borehole, and, by analysing
           the mud  from bottom,  the nature of  the influx.  If  the borehole flowed, the
           well  was  said  to have  kicked;  the  blowout  preventers were closed and the
   330   331   332   333   334   335   336   337   338   339   340