Page 183 - Pipeline Pigging Technology
P. 183

Pipeline  Pigging  Technology


        BACKGROUND


        The  St.Charles Project  for Missouri Pipeline  Co involved  converting  the
     existing 12-in (loop) pipeline to natural gas service. The original pipeline was
     commissioned   for transporting  crude  oil in  1948  and  1961,  and had  been
     abandoned   since  1982.  Upon abandonment, the  pipeline was displaced of
     crude oil and purged with nitrogen. Therefore, the line was expected to be
     in relatively good  condition.
        The  12-in loop line runs from Panhandle Eastern's pipeline  (PEPL) in Pike
     County, Missouri (near  Curryville, MO), to Woodriver,  IL, approximately  85
     miles SE. Various sections and branches of iiew pipeline were included in the
     plans  to  complete  the  loop  line,  including an  11.6-mile  section  of  16-in
     pipeline  between  the Auburn and  Chantilly stations,  and 3.8 miles of  new
     pipeline between  Curryville and the  PEPL tie-in (see  Fig.l).
        In October,  1989,  DS was contacted  by Missouri Pipeline Co for recom-
     mendations  to  clean  the  existing  pipeline  for  conversion  to  natural  gas
     service. The pipeline would be cleaned,  hydrotested, dewatered,  dried and
     placed in service. The primary objectives  set forth for DS were to:

           1. Remove residual crude  oil from  the  pipeline.
           2.  Remove loose  or  adhering  debris which  might cause  operational
              problems in the  pipeline.
           3. Ultimately, clean the pipeline, such that the hydrotest water  would
              meet EPA standards for discharge (i.e. less than or equal to: lOOppm
              suspended  particles,  and 20ppm oil and  grease).
           4. Provide a contingency plan to comply with the parameters in (3), in
              the event that the criteria were not originally satisfied.

        The gellypig service was originally proposed as a single pig train, launched
     at W.Alton, MO, to Curryville, MO. This service would involve exchanging  12-
     in and  16-in mechanical pigs at the Auburn and Chantilly stations, as the  pig
     train enters  and leaves the  11.6 mile section  of new  16-in  pipeline.
        An alternative approach was proposed and selected by Missouri Pipeline,
     such  that  the  operation  would  be  completed  in two distinct  phases  (two
     gellypig trains), as follows:

           Phase 1 - from WAlton to Chantilly Station (approximately  41.5 miles
              of  12-in pipeline)
           Phase  2 - from  Auburn Station to  Curryville Junction  (approximately
              24.6 miles of  12-in pipeline)


                                       164
   178   179   180   181   182   183   184   185   186   187   188