Page 397 - Pipeline Pigging Technology
P. 397

Pipeline Pigging  Technology



      line, would be installed next to it. The pipeline spool would be removed and
      replaced by dogleg spoolpieces to tie in the wye. The pipeline  system would
      then be leak tested  and p re-corn missioned.
         The two valves on each branch allow either branch to be isolated whilst
      the rest of the pipeline  system is operational. This function could be used, for
      instance,  during  a  pipeline  repair,  for  tying-in  another  pipeline,
      decommissioning a branch line, or pressure testing an ESD valve. It is always
      worth considering,  however, whether  all the valves are strictly justifiable.
         At a later date the entrant pipeline would be installed and connected  to the
      spare branch. In the case of a gas line, it would normally be dewatered  to a
      pre-commissioning valve, a spoolpiece would  be connected  across  to  the
      wye,  tested  and  blown  down,  and  the  entrant  pipeline  dried  prior  to
      commissioning.  An entrant  to  an  oil  system  could  avoid  the  extra  pre-
      commissioning valve by testing against the wye valves and dewatering back
      to the platform. Again, there  are many variations on this depending  on  the
      relative timing of the main pipe, wye and entrant pipe installations.




         WYE vs RISER        CONNECTION


         The main alternative to a wye junction is to connect  the second pipeline
      via a riser. Fig.8 compares the field configurations resulting from wye and riser
      tie-ins. Several advantages and a few disadvantages arise from having the wye
      as opposed to the riser as discussed below.  First the  advantages:

            Safety:  as can be seen from Fig.8, the wye junction eliminates the need
               for  an additional import  riser  on the  platform, and is thus a  safer
               solution  from  the  viewpoint  of the  platform, particularly for gas
               pipelines.
            Field layout  The wye junction can be  sited  away from the  platform
               avoiding  seabed  congestion  around the  platform. This leaves  the
               field free to be  developed  using satellite  wells  and flowlines, for
               example, without being crowded by incoming pipelines from other
               fields. It  also  allows  the  field  layout to  be  planned  with  greater
               certainty,  keeping  pipelines  and  flowlines  in  corridors  with  safe
              anchoring areas between,  avoiding spoolpieces under boat-loading
              areas,  etc.
            Cost. The wye will normally show cost advantages over a riser, particu-
              larly if the riser has to be retro-fitted,  or a cantilever extension  has
               to be added for the pig receiver.  If, however, the wye has to be retro-

                                       378
   392   393   394   395   396   397   398   399   400   401   402