Page 399 - Pipeline Pigging Technology
P. 399

Pipeline  Pigging  Technology


              fitted  in an existing pipeline,  then  the  costs  could  go either way,
              depending  amongst other things on the pipeline  lengths, the dura-
              tion  of the  required  shut down,  and  any penalty  associated  with
              making the new line the  same size as the existing.
           Tie-in:  Tying-in  at  a  wye  can  be  done  without  shutting down  the
              existing  system. This has recently been demonstrated  by the  Gyda
              tie-in. In comparison,  construction  work  on a platform  to tie-in an
              entrant is likely to be more disruptive.
           End  of field  life:  If  import  risers  are  used  and  the  original  field  is
              depleted  before  the  end  of the  pipeline  life,  it would  need  to  be
              maintained as a riser platform, or a subsea junction inserted.  Using
              a  wye  junction  allows  the  original  platform  to  be  isolated  and
              decommissioned  without  affecting  the rest of the pipeline  users.
           Emergency   shut  down:  If  import  risers  are  used  and  there  is  an
              emergency shutdown on the platform, the upstream fields will also
              have to be shut down,  whereas  a wye junction would  keep  them
              operating  independently.
           Shorter  line: A wye  junction  can  be  placed  to  give  the  entrant  the
              shortest  pipeline  route. This is particularly so for a retro-fitted  wye.


        Wye junctions also have some drawbacks, and are by no means always the
     best solution for tying-in an entrant. The main drawbacks are as follows:

           Same size line: The wye junction's main use is to connect  entrants of
              the same size as the original pipeline. Whilst it is possible to connect
              other sizes, these would not be piggable. There is typically a cost and
              technical balance for an entrant between  having, say, a smaller non-
              piggable  line  to  a  tee,  a  larger  piggable  line  to  wye,  or  a  longer
              piggable line to a riser.
           Subsea valves and protection covers: It would be feasible to have a wye
              without valves. However, they are normally an operational require-
              ment. For example, to tie-in an entrant without affecting  the rest of
              the  system would  normally need  two  valves on the  branch of the
              wye to give double-block-and-bleed isolation. For this reason,  most
              wyes  to  date  have two  isolation valves on  each  branch.  If subsea
              valves are used, it is necessary to have a protection cover.
           Reverse  pigging:  Whilst  not  normally  required  in  operation,  it  is
              sometimes desirable to be able to pig in reverse during commission-
              ing, for example in dewatering a line from the shore to the platform.
              This would cause technical problems at a wye junction which is only
              piggable in the convergent  directions, and would require some form
              of deflector  plate for reverse  pigging.
                                       380
   394   395   396   397   398   399   400   401   402   403   404