Page 123 - Pipeline Risk Management Manual Ideas, Techniques, and Resources
P. 123

511 00 Design Index
            The comparison between the actual and the required  wall   additional  stresses  anticipated.  Surge pressures,  extreme
           thickness is most easily done by using a ratio of the two num-   temperatures,  or  other  loadings  are  extremely  unlikely.
           bers.  Using  a ratio  provides  a  numerical  scale from  which   The total required wall thickness is therefore 0.60 + 0.08 =
           points can be assigned. If this ratio is less than one, the pipe   0.68 in.
           does  not  meet  the  design  criteria-there   is  less actual  wall   The actual pipe wall thickness installed is a nominal 0.88 in.
           thickness than is required by design calculations. The pipeline   Manufacturing tolerances allow this nominal to actually be
           system has not failed either because it has not yet been exposed   as thin as 0.79 in. No documented thickness readings indi-
           to the maximum designconditions or because some error in the   cate that the line is any thinner than this 0.79-in. value and
           calculations or associated assumptions has been made. A ratio   recent  integrity  verifications  indicate  no  defects,  so  the
           greater than one means that extra wall thickness (above design   evaluator uses 0.79 as the actual wall thickness.
           requirements)  exists. For instance,  a ratio of  1.1 means  that   The ratio of actual to required wall thickness is therefore
           there is 10% more pipe wall material than is required by design   0.79  + 0.68 = 1.16. Therefore, 16% of additional protection
           and 1.25 means 25% more material.            against external damage or corrosion exists.
            The  actual wall thickness  should  account  for  all possible   The point value for 16% extra wall thickness is 5.6, using the
           weaknesses, as discussed earlier and again in the integrity veri-   equation given earlier.
           fication variable. This can be done using detailed stress calcula-
           tions (see Appendix C) or through derating factors devised by
                                                      ~~~~~~~~              -   ~
           the evaluator.                             Example 5.2: Calculating the safety factor
            When all issues have been considered, a simple point sched-
           ule such as that shown in Table 5.1 can be employed to award   Another section of cross-country steel pipeline is being eval-
           points  based on how much extra wall thickness  exists. This   uated. Hydrocarbon liquids are being transported here. In this
           schedule uses the ratio of actual pipe wall to pipe wall required   case, original design calculations are not available. The line is
           and calls this ratio t.                    35 years old and is exposed to varying external loadings. The
            A simple equation can also be used instead ofTable 5.1. The   evaluator proceeds as follows:
           equation
                                                      1.  Because of the age of the line and the absence of original
                        (t- 1) x 35 =point value        documents, the most recent hydrostatic test pressure is used
                                                        to determine  the maximum  allowable  stress for  the  pipe
            yields approximately the same values and has the benefit of   material.  Using  the  test pressure  of 2200 psig,  the stress
           more discrimination between differences in t.   level is calculated to be 27,000 psi (see Appendix C). The
                                                        evaluator is thus reasonably sure that the pipeline can with-
           Table 5.1  Point schedule based on extra wall thickness   stand a stress level of 27,000 psi. The maximum operating
                                                        pressure  of  the  line  is  1400 psig.  Using  this value  and a
                                                        stress level of 27,000 psi, the required wall thickness (for
           f                  Points
                                                        internal pressure only) is calculated to be 0.38 in.
           11.0            -10 WARNING                2.  Using some general calculations  and the opinions  of the
           1.0-1.1             3.5                      design  department,  the  evaluator  feels that  an  additional
           1.1 1-1.20           7                       10% must be added to the wall thickness to allow for exter-
           1.21-1.40           14                       nal  loadings  for  most  conditions.  This  is  an  additional
           1.41-1.60           21                       0.04 in.  He  adds  an  additional  5%  (total  of  15% above
           1.6 1-1.80          28
           >I21                35                       requirements  for  internal  pressure  alone)  for  situations
                                                        where the line crosses beneath roadways. This 5% is thought
                                                        to account for fatigue loadings at all types of uncased road
                                                        crossings, regardless of pipeline depth, soil type, roadway
             Some examples to illustrate the pipe component ofthe safety   design,  and  traffic  speed  and type. In other  words,  15%
           factor follow.                               wall thickness above that required for internal pressure only
                                                        is the requirement  for the worst case situation. This is an
                              ~~~~
           Example 5.1: Calculating the Safety Factor   additional  0.06 in.  for  sections  that  have  uncased  road
                                                        crossings.
             A  cross-country  steel  pipeline  is  being  evaluated.  The   3. Water hammer effects can produce surge pressures up to 100
           pipeline transports natural gas. Original design calculations are   psig.  Such  surges  could  lead  to  an  internal  pressure  as
           available. Pipe is the only type of pipeline component in the   high as  1500 psig (100 psig above MOP). This additional
           segment being assessed. The evaluator feels that no extraordi-   pressure requires an additional 0.02 in. of wall thickness.
           nary conditions exist on the line and proceeds as follows:   4.  The requiredminimum wall thicknesses are therefore 0.38 +
                                                        0.06 + 0.02 = 0.46 in. for sections with uncased crossings,
           1.  He uses information from the design file to determine the   and 0.38 + 0.04 + 0.02 = 0.44 in. for all other sections.
             required wall thickness. A MOP of 2000 psig using a grade   5.  The  evaluator next  determines the  actual  wall  thickness.
             of  steel  rated  for  35,000-psi  maximum  allowable  stress   Records  indicate  that  the  original  purchased  pipe  had  a
             yields a required wall thickness of 0.60 in, for this diameter   nominal wall thickness of 0.65 in. When the manufacturing
             of pipe (see Appendix C). External load calculations show   tolerance is subtracted from this, the wall thickness is 0.58
             the need for an additional 0.08 in. in thickness to handle the   in. Field personnel,  however, mention that wall  thickness
   118   119   120   121   122   123   124   125   126   127   128