Page 27 - Pipeline Risk Management Manual Ideas, Techniques, and Resources
P. 27

they reach the end of their useful service life. Where a time-
                                                     dependent failure mechanism (corrosion or fatigue) is involved,
                                                     its effects will be observed in this wear-outphase of the curve.
                                                     An examination of the failure data of a particular system may
           ul                                        suggest such a curve and theoretically tell the evaluator what
           2?
           -                                         stage the system is in and what can be expected. Failure rates
           .-
           3
           m            I                            are further discussed in Chapter 14.
           LL           I
           c            I
           0            I                            Consequences
           t
           n            I                            Inherent in any risk evaluation is a judgment of the potential
                        I
           f
                        I
           z                                         consequences. This is the last of the three risk-defining ques-
                        I             I              tions: If something goes wrong, what are the consequences?
                        I             I
                                                       Consequence  implies  a  loss  of  some kind.  Many  of  the
                                      !
                        I   Time -                   aspects of potential losses are readily quantified. In the case
                                                     of a major hydrocarbon pipeline accident (product escaping,
                                                     perhaps  causing  an  explosion  and  fire),  we  could  quantify
          Figure 1.1  Common failure rate curve (bathtub curve)   losses such as damaged buildings,  vehicles, and other prop-
                                                     erty; costs of service interruption; cost of the product lost; cost
                                                     of  the  cleanup;  and  so  on.  Consequences  are  sometimes
            Some pieces of equipment or installations have a high initial   grouped into direct and indirect categories, where direct costs
          rate of failure. This first portion of the curve is called the burn-   include
          inphase or infant mortalityphase. Here, defects that developed
          during initial manufacture  of a component cause failures. As   Property damages
          these defects are eliminated, the curve levels off into the second   Damages to human health
          zone. This is the so-called constant failurezone and reflects the   Environmental damages
          phase where random accidents maintain a fairly constant fail-   Loss ofproduct
          ure rate. Components that survive the bum-in phase tend to fail   Repair costs
          at a constant rate. Failure mechanisms that are more random in   Cleanup and remediation costs
          nature-third-party   damages  or  most  land  movements  for
          example-tend  to drive the failure rate in this part of the curve.   Indirect costs can include litigation, contract violations, cus-
          Far into the life of the component, the failure rate may begin   tomer dissatisfaction, political reactions, loss of market share,
          to increase. This is the zone where things begin to wear out as   and government fines and penalties.
            Failures
                            Third-party; earth movements;
                            material<defects                 Corrosion; fatigue












                                                 Time -




                                     Figure 1.2  Theorized failure rate curve for pipelines.
   22   23   24   25   26   27   28   29   30   31   32