Page 336 - Pipelines and Risers
P. 336

Route Optimization, Tie-in and Protection                            309


         173.2 Lateral Pull
         General Principle
         Lateral deflection involves positioning the flowline end to one side of the target structure and
         then pulling it laterally into position. This has two disadvantages compared with a direct pull-
         in.


         -   Alignment is more difficult to achieve;
         -   A clear (swept) area is required to one side of the tie-in site.


         The flowline may be pulled towards the target by a single wire, or a series of  wires may be
         developed through dead-man anchors to give greater control of  alignment. A bell mouth or
         stab-in guides usually assist final alignment.


        For large diameters such  as export lines  or bundles,  it  is  necessary  to  make  a  length  of
        pipeline neutrally buoyant, This gives greater flexibility and reduces the pull  forces, but can
        expose the pipe to large current forces.


        One  development of  this  technique  is  the  use  of  vertical  deflection  rather  than  lateral
        deflection. The required initial shape could be  attained by  local adjustments to buoyancy,
        pull-in being again by a system of wires. The principal advantage of this method is that it does
        not require the same amount of seabed space.


        In addition, it should be possible to devise initial configurations which it would be difficult to
        create laterally by  laying or towed installation. Direct pull for second end tie-ins may then
        become available by creating a vertical slack loop behind the pullhead.


        Installation CapabilitiedConstraints
        This method is usually utilized when direct pull-ins (i.e. J-tube, connect and lay away or stalk-
        on) are not feasible options. However, this method is frequently used as direct pull-ins are
        usually  not  possible. For  instance J-tube  pull-in  and  connect  and  lay  away can  only  be
        performed by a vessel laying away, and not when a vessel lays down. Stalk-ons can only be
        performed in shallow water.

        The main disadvantages  of this method are:


        -  Requires extensive diver intervention;
        -  Difficult  operation  to  perform;  several  experienced  diving  operators  have  buckled
           flowlines using this method;
        -   If  connected directly to the tie-in point then all the pipeline expansions will be fed into
           that point. The tie-in point must either take high axial loads or large deflections.
   331   332   333   334   335   336   337   338   339   340   341