308 Chapter I7
The obvious disadvantages are that remedial work is required after flowline installation to tie
the line in. Additional work requires divers. This could limit this option should the tie-in be
required in very deep waters.
SPOOLPIECE
IATERAL PULL
- PIPELINE IS INITIALLY INSTALLED
PAST ME JACKET
- PIPELINE IS LIFTED AND MOVED
ACROSS TO TIE-IN POINT
J-TUBE PULL
u,, STALK-ON
Figure 17.1 Tie-in methods.