Page 406 - Pipelines and Risers
P. 406

Use of High Strength Steel                                           373

         19.3.2  Field Welding Project Experience
         Onshore capabilities for mechanized and  manual welding have  been  demonstrated by  the
         projects listed in Table 19.4, specific details are given in Chaudhari et al. (1995), Graf et al.
         (1993).

        Manual Welding
        The  quality  requirements of  the  Mega1  11  and  Ruhrgas  lines  required  development  of  a
        welding procedure to overcome concerns over cold cracking of the high strength weld metal
        during conventional vertical-down welding with cellulosic electrode. The technique adopted
        used conventional cellulosic electrodes for the root and hot passes and basic electrodes for the
        fill and cap passes. The root was welded with  an  under-matched consumable, whilst over-
        matched consumables were used for the fill. All welding was downhill.


                   Pass                          Consumable
                                  Trpe    I   AWS Designation  I   Diameter(mm)
                 Root Pass      cellulosic   I    E6010              4
                 Hot pass       C e 11 u 1 os i c   E9010-G          5
                Filler passes     Basic         E10018-G            4.4.5
                 Cap passes       Basic         E10018-G             4




        It should be noted that downhill welding is the norm for pipelines, at least outside of Japan,
        because it is fastest overall. Downhill is conventionally used with cellulosic electrodes which
        have  a finite moisture  content  and are therefore not  ‘low hydrogen’  but  can  be  used  on
        conventional linepipe steels when  other suitable precautions are taken to prevent hydrogen
        cracking. Apart  from pipelines, downhill welding is regarded as  a poor  practice for high
        quality welding and so it appears that the Japanese uphill practice is more cautious.

        High strength steels and weld metals are more sensitive to hydrogen cracking. They cannot be
        reliably welded with  cellulosic electrodes and so  ‘low hydrogen’ consumables are required
        such  as  basic  electrodes which  are  normally  used  in  the  uphill  practice  as per  Japanese
        practice. It appears that cellulosic electrodes were used vertical down on the Ruhrgas line but
        only after 2 weeks special training of welders.

        This  approach  allowed  conventional  welding  of  the  first  two  passes  without  loss  of
        productivity or risk of  cold  cracking. Chaudhari et  al. (1995) states that  the use  of  basic
        electrodes caused only a small loss of productivity for the subsequent passes. This is based on
        an overall welding cycle time of  5 - 6 hours which includes 3.3 hours for moving equipment
        between joints, setting up, etc. If  only the welding time is considered Chaudhari et al. (1995)
        shows the time to complete a joint was 103 minutes using cellulosic electrodes (for all passes)
        compared with  137 minutes  using  basic,  low  hydrogen electrodes. At  33%, the increased
        welding  time  is  significant  and  a  consequence  of  requiring  the  improved  mechanical
   401   402   403   404   405   406   407   408   409   410   411