Page 524 - Pipelines and Risers
P. 524

Design Examples                                                       491

        flowline. It was further concluded that if  a more sophisticated approach was used, this could
        reduce the high cost of large-scale span corrections. The adopted approach was to allow both
        in-line and cross-flow VIV to occur provided it is demonstrated that the allowable fatigue
        damage is not exceeded in  the span during the design life. The methodology used  was  in
        accordance with  the recommendations given by the Multispan project. For VIV, the natural
        frequency of a span is both a function of the span lengwshape, effective force and restraint at
        the shoulder. The conventional approach does not account for the effective force or the actual
        shoulder constraints. This project assessed the natural frequencies of the spans by developing
        a 2D FBM modal multispan analysis model, which takes the in-situ condition of the pipe into
        consideration.


        This approach typically reduced the number of  spans requiring corrections to prevent VIV
        from 20 spans to 2-3 spans for a lOkm production flowline.


        Buckling Control
        It was apparent that the behavior of a high pressure - high temperature flowline resting on a
        very uneven seabed is extremely complex yet the cost of installing and maintaining full cover
        protection would be exorbitant. In order to gain further insight into how  expansion, seabed
        friction and free spans influence each other as the flowlines heat up, non-linear Elasto-Plastic
        2D and 3D FE models were developed in which the available seabed survey data is imported
        directly into the model. As a result of  these studies and  the improved understanding of  the
        buckling behavior, a cost-effective seabed intervention strategy was adopted. Global buckling
        is controlled by  allowing the flowline expansion to be  absorbed into spans and to  further
        control the expansion behavior by using strategically placed discrete rock berms.


        Note that results from these studies were published at the ISOPE’97 conference- See Tames
        et al. (1997) and Nystram et al. (1997).


        The adopted intervention strategy is estimated to give a  saving of  300 million NOK  ($40
        million  US)  compared  to  a  conventional design  in  which  the  flowlines are trenched  and
        buried.

        Wall thickness design
        With the right control of  the material characteristics for linepipe manufacture it was possible
        to use a hoop stress usage factor of 0.80.


        Reliability design
        Corrosion  allowance is optimized using  reliability methods.  A  thicker pipe  wall  may  not
        reduce  operational  and  maintenance  costs,  even  at  the  expense  of  increased  initial
        construction costs.  It  is  therefore necessary  to  optimize the  life  cycle costs  in  the  wall-
        thickness design, by investing in measures that have greater effects on corrosion resistance.

        When  carbon steel pipe is used corrosion allowance is to be  added to the minimum wall-
        thickness. Nedland et al. (1997) conducted a detailed study on the corrosion engineering and
   519   520   521   522   523   524   525   526   527   528   529