Page 526 - Pipelines and Risers
P. 526

Design Examples                                                       493

        The cost of the pipeline was estimated at approximately 7 billion NOK ($1 billion US), where
        approximately 66% is material costs, 29% installation costs, 2% management and design and
        the remaining 3% insurance and miscellaneous items.

        26.3.2  Design Approach
        The project  approach was to focus the design effort where the largest cost benefits to the
        project could be made. The areas that were focused on were:


        Wall thickness design
        With tight control of the material characteristics for linepipe manufacture and welding during
        installation it was possible to have a hoop stress usage factor of  0.80. This results in a 10%
        saving in wall thickness, representing a 5% saving of the overall development cost.


        Reliability design: the transported gas presented some potential corrosion risk to the pipeline
        over  the  50  year  design  life.  Based  on  conventional  approaches  a  nominal  corrosion
        allowance of 3mm was defined which would accommodate a limited number of  ‘upsets’. This
        approach was reviewed based on  the increased ‘reliability’ of  adding corrosion  allowance
        compared with  having no corrosion allowance and controlling the number of  ‘upsets’.  The
        increased reliability of  the system with  and without the corrosion allowance was relatively
        small - and on this basis it was recommended to not  have the corrosion allowance and use
        some capital to better control the potential upsets. The saving would represent 5%  of  the
        overall development costs. However, the project elected not to proceed with this approach due
        to the uncertainties of gas composition of the 5 future tie-ins dong the AT route.


        Pressure control regulation: the normal  design is based  on  incidental pressures going up to
        110% of  design pressure during operation. If  the system can ensure that incidental prcssurc
        does not exceed 105% then the wall thickness can be reduced accordingly. This represented a
        3% saving in wall thickness corresponding to another 1.5% saving in the overall development
        cost. However, the project elected not to proceed with this approach due to the uncertainties
        of controlling the incidental pressure from the 5 future tie-ins along the AT route.


        Intervention design
        Due  to  the  extremely  rough  terrain  a  conventional  design  approach  represented  an
        intervention cost  of  15%  of  the  overall development cost, this  presented  itself  for  large
        potential optimization.


        Trawl board protection
        Based on stress design a trawl board impact would result in unacceptable stresses, this implied
        that the pipeline would not be permitted to freespan. The design demonstrated, that if strain
        based design could be applied, then the associated bending moments would be low. Removal
        of trawl pullover as a limiting design criteria reduces the intervention by 60%, representing a
        2.5% saving in the overall development cost.
   521   522   523   524   525   526   527   528   529   530   531