Page 22 - Plant design and economics for chemical engineers
P. 22

INTRODUCTION    5
       on detailed specifications can then be obtained from various manufacturers.
       However, as mentioned earlier, no design project should proceed to the final
       stages before costs are considered, and cost estimates should be made through-
       out all the early stages of the design when complete specifications are not
        available. Evaluation of costs in the preliminary design phases is sometimes
       called “guesstimation” but the appropriate designation is predesign  cost estima-
       tion. Such estimates should be capable of providing a basis for company
       management to decide if further capital should be invested in the project.
            The chemical engineer (or cost engineer) must be certain to consider all
       possible factors when making a cost analysis. Fixed costs, direct production costs
       for raw materials, labor, maintenance, power, and utilities must all be included
       along with costs for plant and administrative overhead, distribution of the final
       products, and other miscellaneous items.
            Chapter 6 presents many of the special techniques that have been devel-
       oped for making predesign cost estimations. Labor and material indexes,
       standard cost ratios, and special multiplication factors are examples of informa-
       tion used when making design estimates of costs. The final test as to the validity
       of any cost estimation can come only when the completed plant has been put
       into operation. However, if the design engineer is well acquainted with the
       various estimation methods and their accuracy, it is possible to make remark-
       ably close cost estimations even before the final process design gives detailed
       specifications.

       FACTORS AFFECTING PROFITABILITY
       OF INVESTMENTS
       A major function of the directors of a manufacturing firm is to maximize the
       long-term profit to the owners or the stockholders. A decision to invest in fixed
       facilities carries with it the burden of continuing interest, insurance, taxes,
       depreciation, manufacturing costs, etc., and also reduces the fluidity of the
       company’s future actions. Capital-investment decisions, therefore, must be
       made with great care. Chapters 7 and 10 present guidelines for making these
       capital-investment decisions.
            Money, or any other negotiable type of capital, has a time value. When a
       manufacturing enterprise invests money, it expects to receive a return during
       the time the money is being used. The amount of return demanded usually
       depends on the degree of risk that is assumed. Risks differ between projects
       which might otherwise seem equal on the basis of the best estimates of an
       overall plant design. The risk may depend upon the process used, whether it is
       well established or a complete innovation; on the product to be made, whether
       it is a stapie item or a completely new product; on the sales forecasts, whether
       all sales will be outside the company or whether a significant fraction is internal,
       etc. Since means for incorporating different levels of risk into profitability
       forecasts are not too well established, the most common methods are to raise
       the minimum acceptable  rate  of return for the riskier projects.
   17   18   19   20   21   22   23   24   25   26   27